No law ties a fire strategy to a RIBA stage. RIBA's Plan of Work 2020 makes fire safety a core strategy from Stage 0. The fixed points come from law. In England they are the planning fire statement for relevant buildings, Gateway 2 approval before work starts on a higher-risk building and the Regulation 38 handover no later than completion.

Last reviewed
Reading time
13 minutes
Related service
Fire Strategy Reports
Workers on scaffolding against a clear sky

Is a fire strategy tied to a RIBA stage?

No law links a fire strategy to a RIBA stage. The RIBA Plan of Work is an industry framework published by RIBA, not a statutory process. The fire safety deadlines in the Building Regulations 2010, the Higher-Risk Buildings Procedures Regulations 2023 and the Building Safety Act 2022 are set by events instead: the planning application, the building control application, the start of work, completion and occupation.

The useful question is which of those events your project faces and what the fire strategy must be ready for at each one. The RIBA stages are then a way of planning the work so the strategy is ready in time. A strategy that arrives after the design is fixed can only record decisions. One that starts early can shape them.

Our fire strategy reports page explains what the document covers. If you are not yet sure your project needs one, see do I need a fire strategy.

The RIBA Plan of Work 2020 and fire safety

RIBA describes its Plan of Work (opens in a new tab) as "the definitive model for the design and construction process of buildings". It organises a project into eight stages and explains the outcomes, core tasks and information exchanges at each. The edition on RIBA's site in November 2026 is the RIBA Plan of Work 2020.

RIBA lists the Fire Safety Strategy among the core project strategies in the 2020 Overview (opens in a new tab). It says the strategy forms an integral part of the design and should be integrated from the point at which a building project is identified. RIBA says it continues through the asset management of the building and provides a golden thread of fire safety information.

RIBA also publishes overlays to the Plan of Work on particular subjects. Its current list has six: DfMA, Passivhaus, Security, Inclusive Design, Engagement and Smart Building. None of them covers fire safety. RIBA's fire safety tasks therefore sit in the core Overview.

Fire safety tasks RIBA lists at each stage

The 2020 Overview has a Fire Safety row in its task table for every stage. The summary below paraphrases RIBA's own wording. The stage names are RIBA's.

Fire safety tasks in the RIBA Plan of Work 2020 (RIBA, paraphrased)
StageRIBA stage nameFire safety tasks RIBA lists
0Strategic DefinitionAppraise the high-level fire safety suitability of the site, particularly fire service access and means of escape. Identify relevant fire policy and legislation. Review feedback from earlier projects. Decide whether the client team needs specialist fire safety expertise
1Preparation and BriefingGather stakeholder feedback on access, occupant behaviour, use, maintenance and insurance needs. Set overarching fire safety requirements in the Project Brief, including fire service access and the number and location of cores. Collect site information such as fire strategies for existing buildings. Decide whether a specialist fire safety consultant is needed and appoint one
2Concept DesignDevelop the concept in line with the fire safety strategy and the brief, with input from building control bodies and the fire and rescue authority where appropriate. Address warning and escape, external fire spread and fire service access. Record key fire safety decisions in the strategy. Clarify and agree the route to Building Regulations compliance
3Spatial CoordinationTest the design through design studies and engineering analysis. Review Part B, Part A, Part M and regulation 7. Integrate fire safety measures into the coordinated design. Record risks and any deviation from the strategy. Establish specialist subcontractor input such as fire stopping
4Technical DesignPrepare technical design and specifications for passive and active fire protection, escape and firefighting access. Check cost-saving alternatives against fire safety outcomes. Close down fire safety design risks. Address Part B, Part A, Part M and regulation 7 in full and submit the Building Regulations application
5Manufacturing and ConstructionBuild and inspect the fire safety measures, resolve site queries and commission fire protection and life safety systems. Update fire safety information for the Building Manual. Leave no fire safety measures outstanding on the defects list before practical completion
6HandoverHand the fire safety information in the Building Manual to the client. Train building users and facilities managers. Close out fire-related defects. Carry out an initial fire risk assessment
7UseManage the building as set out in the fire strategy. Carry out regular fire risk assessments. Update fire safety information after changes in management, maintenance or refurbishment

RIBA names the fire engineer first among its examples of specialist consultants. Its example is that the fire engineer's calculations might dictate how the design of an atrium develops. Bringing that input in at Stage 1 means it can shape the concept rather than react to it.

RIBA's tasks are good practice, not law. A project can follow them closely and still miss a statutory deadline if the programme does not allow for it. The statutory points are set out next.

The statutory points at a glance

The table sets out the fixed points for a project in England. The last column gives where RIBA places the planning and Building Regulations applications and, for completion, the RIBA stage at which handover happens. RIBA's placement is its own guidance. The basis in the third column is what sets the deadline.

Statutory fire safety points in England and where RIBA places them
EventFire safety materialBasisRIBA stage
Planning application for a relevant buildingGateway 1 fire statement. In London, a D12 Fire Statement for major developmentDMPO 2015 article 9A. London Plan Policy D12End of Stage 3
Building control application for a higher-risk buildingFire and emergency file, often known as a fire strategy. The principal designer must be appointed firstHigher-Risk Buildings Procedures Regulations 2023. Building Regulations 2010 regulation 11DDuring Stage 4, before work starts on site
Full plans application for other buildingsPlans for the local authority, which must consult the enforcing authority where the Fire Safety Order appliesBuilding Regulations 2010 regulation 15ADuring Stage 4, before work starts on site
Completion of a higher-risk buildingCompletion certificate application (Gateway 3) and registration before occupationBuilding Safety Act 2022 section 76. Higher-Risk Buildings Procedures Regulations 2023 regulation 41Stage 6, Handover
Completion or earlier occupation of work that Regulation 38 coversFire safety information handed to the responsible personBuilding Regulations 2010 regulation 38Stage 6, with information built up in Stage 5

Our guide to the Building Safety Act gateways explains how the three gateways fit together.

Planning: the fire statement

In England an application for planning permission for a relevant building must be accompanied by a fire statement about the fire safety design principles, concepts and standards that have been applied to the development. This is article 9A of the DMPO 2015 (opens in a new tab). It applies to applications made on or after 1st August 2021. A relevant building contains two or more dwellings or educational accommodation and is either 18 metres or more in height or has 7 or more storeys. Outline applications and section 73 applications are exempt.

RIBA's Plan of Work says a planning application can be submitted at the end of Stage 3, once the client has signed off a Stage Report. It notes that an earlier submission needs a mid-stage gateway so the information threshold for an application is met. Either way the fire statement will need to reflect decisions already made, such as the number of stairs, fire service access and the approach to the external walls.

The planning statement is not the full strategy. Planning Practice Guidance (opens in a new tab) says a fire statement "should not contain the breadth and depth of information on fire safety which will be submitted at building control application stage". BSR also says applicants should not infer that a comprehensive review of building regulation matters has been undertaken at Planning Gateway One.

For outline or hybrid schemes, the Planning Portal (opens in a new tab) says BSR will usually request that the local planning authority imposes a condition requiring a fire statement form with the reserved matters application. Our guide to the Gateway 1 fire statement covers its content.

London asks for more. Paragraph 3.12.2 of the London Plan 2021 (opens in a new tab) says applicants should consider issues of fire safety before building control application stage. Policy D12(B) says all major development proposals should be submitted with a Fire Statement. The plan also says sprinklers and stair cores that allow simultaneous evacuation should be explored at an early stage. See our guide to London Plan Policy D12 and our planning fire statements service.

Building control: approval before work starts

For a higher-risk building in England you need building control approval from the Building Safety Regulator before starting work. This is Gateway 2. An application to build a new higher-risk building or to carry out category A work to an existing one must include a fire and emergency file. BSR's guidance on preparing an application (opens in a new tab) says "The fire and emergency file is often known as a 'fire strategy'."

Under regulation 11D (opens in a new tab) of the Building Regulations 2010, the principal designer for higher-risk building work must be appointed before that application is submitted. On any other project the appointment must be made before the construction phase begins.

The plans BSR sends to the fire and rescue authority must include the fire and emergency file. That consultation lasts at least 15 working days. BSR must decide an application for a new higher-risk building within 12 weeks and one for work to an existing higher-risk building within 8 weeks, under the Higher-Risk Buildings Procedures Regulations 2023 (opens in a new tab). For staged applications BSR says it will take up to 12 weeks to assess each stage.

Actual times have been longer than the statutory period. BSR's published application data (opens in a new tab) gives a median approval time of 20 weeks for new higher-risk buildings and conversions over the rolling 12 weeks to 1st November 2026. For complex cases over the same period the median was 35 weeks. BSR guidance also says approval lapses after 3 years if work has not reached commencement.

In RIBA terms the Gateway 2 strategy is a Stage 4 document. RIBA says a Building Regulations application should be made during Stage 4, before work commences on site. On a higher-risk building the programme should allow for the decision period before the contractor is due to start. Our building safety gateway support service and our guide to the Gateway 2 fire strategy cover that stage.

For other buildings in England, GOV.UK says a local authority decides a full plans application within 5 weeks or, with your consent, 2 months. Where the Fire Safety Order applies to the building, regulation 15A (opens in a new tab) has required the local authority since 1st October 2023 to consult the enforcing authority before deciding the application. On the registered building control approver route, the approver must not give a plans certificate or a final certificate until 15 working days have passed from its own consultation with the enforcing authority. Our guide to what building control looks for covers that route.

Completion: Gateway 3 and Regulation 38

Regulation 38 (opens in a new tab) of the Building Regulations 2010 says the person carrying out the work "must give fire safety information to the responsible person no later than" one of two dates. Where the building or extension is not occupied during the work, it is the date of completion or the date of occupation, whichever is earlier. In any other case it is the date of completion.

RIBA's glossary describes this timing in different words. Rely on the regulation itself, which sets the latest date for handover. The person carrying out the work must then notify the authority within 5 days of handover. For work under a self-certification scheme the period is 30 days.

Approved Document B says that where a fire safety strategy has been prepared as part of the design and construction process, it should be made available to the relevant dutyholder. That is paragraph 17.3 of Volume 1 (opens in a new tab) and paragraph 19.3 of Volume 2 (opens in a new tab). RIBA's Stage 5 and Stage 6 tasks build up exactly that information. Our guide to Regulation 38 explains what the pack should contain.

For a new higher-risk building in England, occupying a relevant unit before a completion certificate is issued is an offence under section 76 of the Building Safety Act 2022 (opens in a new tab), in force since 1st October 2023. New higher-risk buildings must also be registered before residents can occupy them. BSR must decide a completion certificate application within 8 weeks. Our guide to Gateway 3 covers the evidence needed.

The timing may become stricter. The Grenfell Tower Inquiry's Recommendation 10 asks for a fire safety strategy produced by a registered fire engineer to be submitted at Gateway 2 for higher-risk buildings and reviewed and resubmitted at Gateway 3. The government accepted it and gave its status as In progress in the progress report (opens in a new tab) updated on 2nd October 2026.

What official guidance says about timing

Official guidance asks for early fire safety input. It speaks of early engagement rather than RIBA stage numbers.

  • Approved Document B says anyone who prefers to meet a requirement in a way other than the approved document describes should seek to agree this with the relevant building control body at an early stage.
  • BB100, the schools guide, says fire safety engineering will be most effective if it is included in the overall design process at the earliest possible opportunity. It says design teams must allocate time to consult enforcing bodies and property insurers at an early stage. The DfE Technical Manual now says BB100 is no longer required for DfE projects.
  • HTM 05-02 says the fire safety measures and the evacuation strategy for healthcare buildings should be developed and agreed through discussions with the client user group, the design team, a fire service representative and building control. It recommends a set of fire drawings to assess the fire precautions at design stage.
  • The DfE Technical Manual of January 2026 requires a project specific fire strategy. It refers to RIBA stages only for whole life carbon reporting and does not assign the fire strategy to a stage.

Putting this together, a sensible pattern for most projects is an early appraisal at Stages 0 and 1, a concept strategy at Stage 2, a developed and coordinated strategy at Stage 3 and a full technical strategy at Stage 4. The strategy is then kept up to date through construction and issued as built at handover. That is general professional practice rather than an official rule. Our guides to BB100 and HTM 05-02 cover those sectors.

Wales and Scotland

In Wales the council has been the building control authority for higher-risk buildings since 1st July 2026. Part 2B of the Building Regulations 2010 brings dutyholder and competence duties for building work generally from the same date. For buildings the Fire Safety Order applies to, regulation 15B bars approval until 15 days after the fire authority is consulted unless its views come in earlier. Wales has no Gateway 1 style planning fire statement. Fire and rescue authorities are statutory planning consultees for listed developments validated on or after 25th April 2022. See our guide to fire strategy in Wales and our Wales page.

In Scotland a building warrant is required before construction or conversion under section 8 of the Building (Scotland) Act 2003 (opens in a new tab). A completion certificate follows the work. For a new non-domestic building a fire safety design summary has gone with the completion certificate since 1st October 2013. For high-rise buildings, industry guidance on the Compliance Plan Approach published on 28th May 2026 expects pre-warrant engagement at least 12 weeks before the first building warrant submission. See our guide to fire strategy in Scotland and our Scotland page.

Wherever the project is, the earlier the fire strategy starts, the more it can shape the design. Our fire strategy reports page sets out what the document covers at each stage.

Sources

This guide was written from these official sources. Check the current version before relying on any figure.

Common questions

More on this topic.

All fire strategy questions

No law sets a stage. RIBA's Plan of Work 2020 treats fire safety as a core project strategy from Stage 0 and records key fire safety decisions in the strategy at Stage 2. The full strategy needs to be ready for the Building Regulations application, which RIBA places in Stage 4.

Keep reading

Related guides.

Talk to an engineer

Tell us about the building

Send us the drawings, the building type and the stage you are at. We reply the same day with a clear scope, programme and fixed fee.

  • 01Written in-house by the engineer who will defend it to the approver
  • 02Approved Document B, BS 9999, BS 9991 and BS 7974
  • 03Building Control and fire authority engagement handled for you
  • 04Projects of every size, across the UK

Request a quote

Same-day reply

Only used to reply to this enquiry.

We reply the same day.