What Regulation 38 says
Regulation 38 of the Building Regulations 2010 (opens in a new tab) makes the person carrying out building work give fire safety information to the Responsible Person when the work finishes. It defines fire safety information as information about the design and construction of the building or extension and the services, fittings and equipment provided in it, which will help the Responsible Person to operate and maintain the building with reasonable safety.
Regulation 38 applies in England and Wales, in a separate version for each nation. Scotland has a different rule, covered below. It is the point where the fire design passes from the people who designed and built the building to the people who have to run it. Our Regulation 38 fire safety information service compiles and checks these packs.
Approved Document B (opens in a new tab) sets out the aim in plain terms. It is achieved when the person responsible for the building has all the information to understand and implement the fire safety strategy, maintain any fire safety system and carry out an effective fire risk assessment. A pack that does not let someone do those three things has not done its job.
Which buildings and work it covers
The regulation applies where Part B imposes a requirement on the work and the work is either the erection or extension of a relevant building or work in connection with a relevant change of use. A relevant building is one the Fire Safety Order 2005 (opens in a new tab) applies to or will apply to once the work is complete. A relevant change of use is a material change of use after which the Order will apply or continue to apply.
That ties the scope to the Fire Safety Order. The Order does not apply to domestic premises. A single private house is therefore outside Regulation 38. Where a building contains two or more sets of domestic premises, the Order does apply to the structure, the external walls, any common parts and the doors between the flats and the common parts. So a new block of flats is in scope, as are offices, shops, schools, care homes, hotels and industrial buildings.
Change of use catches people out. Converting an office into flats or a house into a building the Order applies to brings the work within Regulation 38 where Part B imposes a requirement, even if little new construction is involved. The same is true of an extension to an existing building the Order covers.
Who hands over the pack and when
The duty is on the person carrying out the work, which in practice is usually the main contractor working with the design team. The receiver is the Responsible Person as defined in article 3 of the Fire Safety Order. For a workplace that is the employer where the workplace is to any extent under their control. Otherwise it is the person in control of the premises in connection with a trade, business or other undertaking. Where that person does not have control in that way, it is the owner.
The deadline depends on whether the building is in use during the work. If it is not occupied, the information must be given by the date of completion or the date of occupation, whichever is earlier. In any other case it must be given by completion. Approved Document B puts it more simply as completion or first occupation, whichever is earlier. Since its 2025 amendments it uses the term relevant dutyholder, meaning the responsible person or the accountable person.
The practical lesson is to start early. A pack assembled in the last week before practical completion is usually a box of operation and maintenance manuals with no explanation of how the fire safety measures work together. The strategy, the as-built drawings and the commissioning records need to be gathered as the job goes on.
The England changes from 1st October 2023
In England the regulation was amended on 1st October 2023 by the Building Regulations etc. (Amendment) (England) Regulations 2023 (SI 2023/911). Before that it only required the information to be given. It now also requires the handover to be evidenced. The Responsible Person must give the person carrying out the work a notice acknowledging receipt and confirming that the information is sufficient for them to understand, operate and maintain the building and its fire safety systems after the work.
The person carrying out the work must then tell the relevant authority that the information has been given and that the acknowledgement has been received. If no acknowledgement arrives, the notice must instead state the steps taken to obtain it and the dates they were taken. The deadline for that notice depends on how the work is being certified.
| How the work is controlled | Who must be notified | Deadline after the handover date |
|---|---|---|
| Any other building work | The relevant authority (building control) | 5 days |
| Work under a self-certification scheme (regulation 20) | The relevant authority | 30 days |
| Work under a third party certification scheme (regulation 20A) | The third party certifier, who then notifies the relevant authority | 7 days to the certifier, then 30 days for the certifier to notify the authority |
From 1st October 2023 Regulation 38 was also applied, with modifications, to work under the Building (Approved Inspectors etc.) Regulations 2010. It was further modified for England on 6th April 2024 by the Building (Registered Building Control Approvers etc.) (England) Regulations 2024. The regulation itself has not changed in England since then. Approved Document B was brought into line by its 2025 amendments, which took effect on 2nd March 2025. They replaced the regulation 38 text box and rewrote Section 19 of Volume 2 and Section 17 of Volume 1.
Keep a dated record of every attempt to get the acknowledgement. Without it the notice must list the steps taken to obtain the acknowledgement and the dates they were taken. A dated record is the only way to show that.
What should be in the pack
Section 19 of Approved Document B Volume 2 and Section 17 of Volume 1 give the guidance for England. They describe it as a guide and not exhaustive, with the level of detail decided case by case. It notes that information on the location of fire protection measures may be sufficient. The essential information should make clear how the fire safety arrangements are intended to operate together and any fire safety strategy that has been prepared should be made available.
- As-built plans showing escape routes with exit capacity for each storey and for the building
- Fire resisting construction and fire-separating elements, including cavity barriers in walk-in spaces
- Fire doorsets, self-closing devices and other doors relevant to the strategy
- Detection, manual call points, alarm panel, sounders, signage, emergency lighting, extinguishers, fire mains and hydrants
- Sprinkler systems with isolating valves and control equipment
- Smoke control systems with their mode of operation and controls
- High risk areas, power supplies and the location of secure information boxes
- Specifications of fire safety equipment with routine maintenance schedules
- The assumptions about management made in the fire safety design
- Provision for evacuating disabled people, for use in personal emergency evacuation plans
- For care homes, the assessment of the number of beds in a compartment (Volume 2)
Complex buildings need more. The guidance asks for a detailed record of the fire safety strategy and the procedures for operating and maintaining fire protection measures, including an outline cause and effect matrix. The records should cover all design assumptions such as fire load, any risk assessments, the escape strategy and assembly points, every passive and active measure, operators' manuals, software, system zoning, inspection and maintenance schedules and commissioning test records. The government's Approved Document B FAQ adds that maintenance-dependent products, such as a fire retardant coating, should be highlighted in the pack.
Most of this list should already exist in a well written strategy. Our fire strategy report example shows a contents page laid out to feed it. Our guide on what a fire strategy is explains why the strategy sits at the centre of the pack. Healthcare premises have their own list in HTM 05-02.
What happens to the pack after handover
The Responsible Person uses the pack to make and review the fire risk assessment required by article 9 of the Fire Safety Order. When the Responsible Person changes, article 22A requires the outgoing person to pass on relevant fire safety information, which expressly includes information given under Regulation 38. The Responsible Person must keep records of that information. Both articles apply in England and Wales.
In England the Fire Safety (England) Regulations 2022 (opens in a new tab), in force since 23rd January 2023, add duties that build on the pack. In a high-rise residential building, meaning one with two or more sets of domestic premises that is at least 18 metres high or has at least seven storeys, the Responsible Person must keep a secure information box, a record of the external wall design and floor plans and a single page building plan for the fire service. The external wall record and the plans must also be sent to the local fire and rescue authority electronically.
The same regulations require fire safety instructions for residents in any building with two or more sets of domestic premises and common parts used for evacuation. They also require fire door checks in such buildings above 11 metres. Flat entrance doors need best endeavours checks at least every 12 months and communal fire doors at least every 3 months. All of this is easier when the Regulation 38 pack already holds accurate as-built plans and door schedules.
Higher-risk buildings in England
For higher-risk building work in England a separate handover duty applies under regulation 38 of the Higher-Risk Buildings Procedures Regulations 2023 (opens in a new tab). The client, not the contractor, must give the relevant person the fire safety information along with ventilation, energy, electricity generation and overheating information where those parts of the Building Regulations apply, together with the specified golden thread information, by the date the work is completed. Where a partial completion certificate applies the deadline is the date that part of the building is to be occupied. If the building is still a higher-risk building after the work, the relevant person is the accountable person for the part of the building concerned and the responsible person if there is one.
The golden thread information must keep the filing structure in which it was kept, with its indexes and keys, in a format the receiver can read, keep and update. The receiver must give the client a notice confirming they can access the information and that it is sufficient to understand, operate and maintain the building and its fire safety systems. The duty does not apply to work to an existing higher-risk building that consists only of scheme work, exempt work or notified emergency repairs.
The Building Safety Regulator's golden thread guidance (opens in a new tab) says that to apply for a completion certificate the client must show that the information has been given to the accountable person or the Responsible Person as relevant. It also expects accountable persons to understand the fire strategy for the parts of the building they are responsible for. That fire strategy then underpins the safety case, which our guide on what a building safety case is explains.
Regulation 38 in Wales and Scotland
Wales has its own version of Regulation 38. Its handover paragraphs were replaced on 1st July 2026 by the Building etc. (Amendment) (No. 2) (Wales) Regulations 2025. The Welsh version has the same handover deadline and the same acknowledgement notice as England and requires notice to the building control authority within 5 days of handover. For self-certification scheme work the period is 30 days. It has no third party certification paragraphs. When first made the Welsh deadlines were in working days. A further amendment on 20th July 2026 removed the word working from both. The periods now run in days.
| Nation | Rule | Notes |
|---|---|---|
| England | Building Regulations 2010, regulation 38 (England version, amended 1st October 2023) | Acknowledgement by the Responsible Person and notice to building control. Separate client duty for higher-risk building work |
| Wales | Building Regulations 2010, regulation 38 (Wales version, amended 1st July 2026) | Acknowledgement and notice to the building control authority. Separate client duty under the Welsh higher-risk buildings regulations from 1st July 2026 |
| Scotland | Building (Procedure) (Scotland) Regulations 2004, regulation 41(bd) | Regulation 38 does not apply. A Fire Safety Design Summary goes with the completion certificate for a new non-domestic building or a conversion to one |
The Welsh Approved Document B Volume 2 still gives guidance on the pack in its Appendix G, with separate lists for simple and complex buildings. That guidance predates the 2026 changes and does not mention the acknowledgement notice. For higher-risk buildings in Wales, regulation 37 of the Welsh 2025 procedures regulations requires the client to give the fire safety information and golden thread information to the responsible person by completion. The Fire Safety (England) Regulations 2022 do not apply in Wales.
In Scotland the Fire Safety Design Summary has been required since October 2013. It records information about the design and construction of the building and its services, fittings and equipment to assist in its operation and maintenance for fire safety purposes.
When the pack is missing or incomplete
Some Responsible Persons discover at their first fire risk assessment that no pack exists. Others find that what they were given has no fire content. Typical gaps are a strategy that was never updated to match the as-built building, no record of the management assumptions, no door or damper schedules and no commissioning certificates for alarms or smoke control. Approved Document B is clear that a design relying on an unrealistic or unsustainable management regime does not meet the requirements. Those assumptions therefore matter.
Where the information was never produced it can often be rebuilt. A survey of the building, the surviving drawings and the original approvals are often enough to produce a retrospective fire strategy and a pack built from it. Where a pack exists but its quality is uncertain, a fire strategy review will show what is missing before the fire risk assessor finds it.
If you are a contractor approaching completion or a Responsible Person who has inherited a building without its records, our Regulation 38 team can compile, check or reconstruct the information. You can also contact us with the drawings and the stage the project has reached.
Sources
This guide was written from these official sources. Check the current version before relying on any figure.
- Building Regulations 2010, regulation 38 (official source, opens in a new tab)
- Approved Document B Volume 2, 2019 edition incorporating 2020, 2022, 2025 and 2026 amendments (official source, opens in a new tab)
- Approved Document B Volume 1, 2019 edition incorporating 2020, 2022, 2025 and 2026 amendments (official source, opens in a new tab)
- 2025 amendments to Approved Document B volume 1 and volume 2 (official source, opens in a new tab)
- Approved Document B: fire safety frequently asked questions (official source, opens in a new tab)
- Regulatory Reform (Fire Safety) Order 2005, article 3 (official source, opens in a new tab)
- Regulatory Reform (Fire Safety) Order 2005, article 6 (official source, opens in a new tab)
- Regulatory Reform (Fire Safety) Order 2005, article 9 (official source, opens in a new tab)
- Regulatory Reform (Fire Safety) Order 2005, article 22A (official source, opens in a new tab)
- Fire Safety (England) Regulations 2022, regulation 6 (official source, opens in a new tab)
- Fire Safety (England) Regulations 2022, regulation 10 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 38 (official source, opens in a new tab)
- Keeping information about a higher-risk building: the golden thread (Building Safety Regulator) (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025, regulation 37 (official source, opens in a new tab)
- Approved Document B Volume 2, buildings other than dwellinghouses (Wales) (official source, opens in a new tab)