The short answer
In England no Act or regulation defines a fire strategy or requires a document by that name. The government's Grenfell Tower Inquiry progress report (opens in a new tab), updated on 2nd October 2026, states that a fire safety strategy is not a required document to be submitted as part of an application. Our guide to what a fire strategy is covers that point in full.
The practical answer is different. Four routes call for what a fire strategy contains, even where they use another name. Almost any project on a building the Fire Safety Order covers meets at least one of them. Our fire strategy reports service writes the document for each route.
- Full plans for building control. Work to a building the Fire Safety Order applies to now or will apply to after the work must use a full plans application under regulation 12(3) (opens in a new tab) of the Building Regulations 2010, in England and in Wales. The plans have to show that the work would comply and on fire safety that is usually done with a strategy.
- The Gateway 2 fire and emergency file. A new higher-risk building in England needs this file in its application to the Building Safety Regulator. So does category A work to an existing one. The Regulator's guidance says the file is often known as a fire strategy.
- Planning fire statements. Some tall residential schemes in England need a Gateway 1 fire statement. London Plan Policy D12(B) says major developments in London should be submitted with a Fire Statement, which it describes as an independent fire strategy.
- Regulation 38 handover. At completion the fire safety information goes to the Responsible Person. Approved Document B says that where a fire safety strategy has been prepared it should be made available. For complex buildings it asks for a detailed record of the strategy itself.
Where a project falls under more than one route, each has to be met.
Buildings the Fire Safety Order covers
The full plans rule is the route that catches most projects. The Fire Safety Order (opens in a new tab) covers non-domestic premises. In a building with two or more sets of domestic premises it also covers the structure, the external walls, the common parts and the doors between the flats and the common parts. A block of flats is therefore a Fire Safety Order building whatever its height.
Holiday lets catch people out. The government's Approved Document B FAQ (opens in a new tab) says self-catering holiday homes and short-term lets are subject to the Fire Safety Order.
A building notice is not available for these buildings. A full plans application must state whether the Order applies to the building. Under regulation 14 (opens in a new tab) it must also include any other plans necessary to show that the work would comply. Building control then consults the fire service. The consultation pro forma gives a fire strategy as the first example of supplied information. Our guide to what building control looks for covers that process.
The rule may widen. The MHCLG consultation Plan approval requirements for new builds and fire safety order buildings (opens in a new tab) ran from 2nd April 2026 to 11th June 2026. It proposed full plans for all new dwellings on the local authority route and mandatory plans certificates for new dwellings and Fire Safety Order buildings on the private approver route. GOV.UK says the feedback is being analysed. Regulation 12, read on 23rd November 2026, does not yet contain the new dwelling rule.
Project by project
The table shows which routes apply to common projects in England and whether a strategy is needed in practice. Wales and Scotland are covered at the end of this guide.
| Project | What the law asks for | Is a fire strategy needed? |
|---|---|---|
| New non-domestic building or an extension to one (not higher-risk) | Full plans under regulation 12(3), fire service consultation by building control and Regulation 38 handover | In practice yes. It is the usual way to show Part B compliance on the plans and it is handed over at completion |
| New block of flats under 18 metres and under 7 storeys | Full plans because the Fire Safety Order covers the common parts. Regulation 38 handover | In practice yes. In London a D12(B) Fire Statement is also expected for major development |
| Higher-risk building: at least 18 metres or 7 storeys with at least 2 residential units, a hospital or a care home | Building Safety Regulator approval with a fire and emergency file before work starts | Yes in substance. The Regulator says the file is often known as a fire strategy |
| Material alteration to a Fire Safety Order building | Full plans. The work must not leave the building worse on B1, B3, B4 or B5 | Usually an update of the existing strategy, scaled to the work |
| Material change of use, such as offices to flats | Regulation 6 applies B1, B2, B3, B4(2) and B5 in all cases and B4(1) above 11 metres | Usually yes. The building is assessed against Part B in its new use |
| Planning application for a tall residential scheme or London major development | Gateway 1 fire statement for relevant buildings. Policy D12(A) and D12(B) in London | A planning stage strategy usually sits behind the statement |
| Single private house, house extension or loft conversion | Part B still applies. The Fire Safety Order, the full plans rule and Regulation 38 do not | Not normally. No official source checked says one is needed |
| Existing building with no strategy | A fire risk assessment under article 9 of the Fire Safety Order and passing on fire safety information | Not by law. A retrospective strategy is often the practical way to record the design basis |
For a house, Part B still applies to the work even though no strategy is needed. Our guide to loft conversion fire safety covers the provisions for new storeys in houses.
New buildings, extensions and complex schemes
Building work includes erecting or extending a building, a material alteration and work required on a material change of use under regulation 3 (opens in a new tab). Regulation 4 requires the work to comply with Schedule 1, which includes Part B. After an extension the building must comply or, where it did not comply before, be no more unsatisfactory than it was.
The further a design departs from Approved Document B, the more the strategy matters. Approved Document B says that where alternative methods are adopted the overall level of safety should not be lower than the approved document provides. It is the responsibility of those undertaking the work to demonstrate compliance. Fire safety engineering may be the only practical way to achieve a satisfactory standard in some complex buildings, as our guide to fire engineered solutions explains. The government's FAQ says tall, large or complex buildings are not common building situations and that designers should agree the design intent and the necessary evidence with the building control body before starting work.
Upward extensions need particular care. The FAQ says that where a new floor takes an existing building over 11 metres, sprinkler protection will be necessary in the majority of cases in new accommodation above that height. Some guidance names the strategy directly:
- Approved Document B says the design of units in a shopping complex should be compatible with the fire strategy for the complex as a whole.
- Approved Document B says BB100 should be used for schools and BB100 says a clear fire strategy report must be available on site. Our BB100 guide explains how the two relate.
- HTM 05-02 says a detailed record of the fire safety strategy, evacuation procedures, patient dependency and staffing levels will be required for all healthcare premises it covers.
Alterations and change of use
An alteration is material if at any stage it would make a building that complied with a relevant requirement stop complying. It is also material if it would make a building that did not comply more unsatisfactory. The fire requirements on that list are B1 means of warning and escape, B3 internal fire spread (structure), B4 external fire spread and B5 access and facilities for the fire service. B2 internal linings is not on it.
On a Fire Safety Order building the work still needs full plans. Moving a wall around an escape route changes what the original strategy relied on. The sensible course is to update it. Our guide to keeping a fire strategy up to date explains how.
A material change of use under regulation 5 (opens in a new tab) includes a building becoming a dwelling, containing a flat where it did not, becoming a hotel, institution, public building or shop or changing its number of dwellings. Under the England version of regulation 6 (opens in a new tab), after a change of use of the whole building the work must make it comply with B1, B2, B3, B4(2) roofs and B5 in all cases. Where the building exceeds 11 metres B4(1) external walls applies too, a height that has applied in England since 1st December 2022. Where only part changes use, that part must comply and B4(1) still applies to the whole building above 11 metres.
This is why a change of use usually needs a strategy even when little construction is involved. The building is tested against Part B in its new use, not its old one. Permitted development in England has its own trigger. Prior approval under Class MA of Part 3 and Classes A and AA of Part 20 needs a fire safety statement where the planning gateway one height condition is met. Our guide to fire strategy for a change of use covers both.
Higher-risk buildings in England
GOV.UK says you need building control approval from the Building Safety Regulator before starting a new higher-risk building, work that makes an existing building higher-risk or stops it being one and most work on an existing higher-risk building. For design and construction a higher-risk building is at least 18 metres high or at least 7 storeys and has at least 2 residential units or is a hospital or care home. Our guide to what a higher-risk building is covers the test.
The application must include a fire and emergency file under the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 (opens in a new tab), in force since 1st October 2023. This applies to a new higher-risk building and to category A work to an existing one. The Regulator says the file is often known as a fire strategy. On these projects the law requires a statutory file that does the job of a strategy under another name.
Category A work includes work that changes the height, width or number of storeys, flats or residential rooms. It also includes work that affects the passive or active fire safety measures or the common parts, including the external wall. Other work is category B, for which a fire compliance statement may be needed instead. The Regulator can also require a fire and emergency file for category B work by written notice before it decides.
Inquiry Recommendation 10 would make a fire safety strategy by a registered fire engineer a statutory document at Gateways 2 and 3. The government has accepted it and gave its status as In progress on 2nd October 2026. Our guide to the Gateway 2 fire strategy explains what the Regulator expects.
Planning applications
In England article 9A of the Development Management Procedure Order 2015 (opens in a new tab) requires a fire statement with planning applications for relevant buildings. A relevant building is 18 metres or more in height or has 7 or more storeys and contains two or more dwellings or educational accommodation. Outline and section 73 applications are exempt. Hospitals and care homes are not in this test even though they are in the Gateway 2 test.
In Greater London, Policy D12(B) of the London Plan 2021 (opens in a new tab) says all major development proposals should be submitted with a Fire Statement, which it describes as an independent fire strategy produced by a third party, suitably qualified assessor. Major development means 10 or more dwellings or a residential site of 0.5 hectares. For other uses it means 1,000 square metres or a site of 1 hectare. A tall residential scheme in London can need both the Gateway 1 statement and a D12(B) statement.
Neither statement replaces the strategy that goes to building control. Our guide to whether a planning application needs a fire statement sets out the tests. Our planning fire statements service prepares the statement and the planning stage strategy together.
Existing buildings with no fire strategy
No official source says an existing building with no strategy must commission one. The legal duty in occupation is the fire risk assessment. Under article 9 of the Fire Safety Order (opens in a new tab) the Responsible Person must make a suitable and sufficient assessment of the risks, review it regularly and keep a written record. That applies in England and Wales.
The design information still matters. Approved Document B says the aim of Regulation 38 is that the person responsible can understand and implement the fire safety strategy, maintain the fire safety systems and carry out an effective fire risk assessment. When the Responsible Person changes, article 22A requires the outgoing person to pass on relevant fire safety information, including anything given under Regulation 38. A building that never had a strategy has nothing to pass on.
Strategies do go missing. In the first quarter of 2020 London Fire Brigade audited 15 London developments whose common parts relied on mechanical smoke ventilation, 36 cores in all. Its engineer recorded a 50 percent failure rate, core by core, on whether the Responsible Person had a copy of the fire strategy. The figure comes from the Brigade's quarterly fire engineering reports (opens in a new tab) for January 2020 to March 2021, a series that stopped after March 2021.
In England, high-rise residential buildings of at least 18 metres or 7 storeys with two or more sets of domestic premises also need floor plans and a single-page building plan under the Fire Safety (England) Regulations 2022 (opens in a new tab). That duty does not name a fire strategy as such.
A retrospective fire strategy is often the practical way to rebuild that baseline. Our guide to what a retrospective fire strategy is explains when one makes sense.
Wales and Scotland
Wales has its own version of regulation 12(3) with the same full plans rule for Fire Safety Order buildings. Since 1st July 2026 regulation 15B has required the building control authority to consult the enforcing authority and wait 15 days before approval unless its views arrive sooner. Regulation 38 also applies in Wales in its own version.
Welsh higher-risk buildings have had their own regime since 1st July 2026 under the Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025 (opens in a new tab), with the local authority as building control authority. The application needs a fire and emergency file, which the Welsh Government says is often known as a fire strategy. The test covers buildings of at least 18 metres or 7 storeys with at least one residential unit or a hospital, care home or children's home.
Wales has no planning fire statement. Fire and rescue authorities have instead been statutory planning consultees on listed types of application validated on or after 25th April 2022. Our Wales page covers projects there.
Scotland uses building warrants. The Scottish Government's call for evidence (opens in a new tab), published on 16th January 2026, says no provisions specific to domestic buildings mandate a fire safety strategy. Since October 2013 a Fire Safety Design Summary has been required with the completion certificate for a new non-domestic building or a conversion to one. Our Scotland page covers projects there.
If you are unsure which routes apply, send us the drawings and the stage the project has reached. Our fire strategy reports team replies the same day with the documents the project needs and a fixed fee.
Sources
This guide was written from these official sources. Check the current version before relying on any figure.
- Grenfell Tower Inquiry: government progress report, September 2026, the construction industry (official source, opens in a new tab)
- Building Regulations 2010, regulation 12 (official source, opens in a new tab)
- Building Regulations 2010, regulation 6 (official source, opens in a new tab)
- Building Regulations 2010, regulation 38 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 4 (official source, opens in a new tab)
- Preparing information for a building control approval application (Building Safety Regulator) (official source, opens in a new tab)
- Approved Document B Volume 2, 2019 edition incorporating 2020, 2022, 2025 and 2026 amendments (official source, opens in a new tab)
- Approved Document B: fire safety frequently asked questions (official source, opens in a new tab)
- Town and Country Planning (Development Management Procedure) (England) Order 2015, article 9A (official source, opens in a new tab)
- The London Plan 2021, Policy D12 (official source, opens in a new tab)
- Regulatory Reform (Fire Safety) Order 2005, article 9 (official source, opens in a new tab)
- Plan approval requirements for new builds and fire safety order buildings (MHCLG consultation, 2026) (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025 (official source, opens in a new tab)
- Scottish building regulations fire safety review: call for evidence (Scottish Government) (official source, opens in a new tab)