What Gateway 2 is and when it applies
Gateway 2 is building control approval from the Building Safety Regulator (BSR) before building work starts on a higher-risk building in England. BSR's guidance (opens in a new tab) says approval is needed before constructing a new higher-risk building and before work that makes an existing building higher-risk or stops it being so. It is also needed for work to an existing higher-risk building unless the work is only exempt work, competent person scheme work, fibre optic cabling or emergency repairs. Carrying out building work without the required approval is a criminal offence.
For design and construction BSR treats a building as higher-risk if it has at least 7 storeys or is at least 18 metres high and has at least 2 residential units or is a hospital or care home. The guide to what counts as a higher-risk building covers how height and storeys are measured. The Health and Safety Executive, acting as BSR, became the building control authority for these buildings on 1st October 2023. BSR left the Health and Safety Executive and became a standalone body on 27th January 2026.
Developers can no longer choose their building control body for a higher-risk building. The procedure is set by the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 (opens in a new tab), which have been in force since 1st October 2023 and apply in England only. The overview of all three gateways sets Gateway 2 in context. What follows deals with the fire safety part of the application, which is the part our Gateway 2 and Gateway 3 support service is most often asked to prepare.
Is the fire and emergency file the same as a fire strategy?
In practice it is, although the law does not use the words fire strategy. Regulation 4 (opens in a new tab) requires an application for a new higher-risk building to be accompanied by a fire and emergency file. BSR's guidance on preparing an application (opens in a new tab) says the fire and emergency file is often known as a fire strategy. A competent fire strategy is therefore the natural basis for the file, provided it is written to answer what Schedule 1 asks for.
Work to an existing higher-risk building is split into two categories. Category A covers, among other things, work that changes the number or width of staircases or escape routes, work to the external wall, work that changes the internal layout and work that affects the passive or active fire safety measures. A category A application needs a fire and emergency file just as a new building does. Category B is everything else.
For category B work where Part B applies, regulation 12 (opens in a new tab) asks instead for fire safety compliance information. That means the fire safety design principles, concepts and standards applied, with enough plans to show how the work would comply with Part B. BSR's guidance calls this a fire compliance statement and says it may also be known as a fire strategy for the work.
There is still no statutory document called a fire strategy. The government's Grenfell Tower Inquiry progress report (opens in a new tab), updated on 2nd October 2026, says a fire safety strategy is not a required document in an application but that the regime already requires extensive fire safety information. It accepted Recommendation 10 for a statutory fire safety strategy by a registered fire engineer at Gateway 2 and gives its status as in progress.
What the fire and emergency file must contain
Schedule 1 (opens in a new tab) paragraph 5 of the regulations sets the content. The file is built around building safety risks, which section 120G of the Building Act 1984 (opens in a new tab) defines as risks to people in or about a building arising from the spread of fire or structural failure. Regulations can prescribe further matters. The file is therefore wider than Part B alone. It also has to deal with the risk of structural failure.
- The matters considered when assessing how the identified building safety risks could affect the building.
- The proposals adopted and the design approaches taken to comply with the building regulations that relate to those risks.
- The measures, strategies and policies the owner should adopt to manage and maintain the building so that anyone in it can be safely evacuated in an emergency.
- The assumptions made about the intended occupiers and their likely characteristics and behaviours.
- A plan setting out the fire and rescue service's requirements for access to the building and water supply for firefighting.
- A report that demonstrates how compliance with the building regulations relating to the building safety risks is to be achieved.
BSR's guidance puts the same requirements in Part B terms. The file must include plans showing how the work provides adequate means of escape and warning, measures to inhibit fire spread inside and outside the building and reasonable access and facilities for the fire service. It must also explain how the owner will manage and maintain the building so it can be evacuated, including the behaviour of the occupiers.
The management content deserves as much care as the design content. A strategy that relies on a stay put or phased approach, a sprinkler system or smoke control is making assumptions about how the building will be run for decades. Schedule 1 asks for those assumptions to be written down at Gateway 2 rather than discovered at handover. The guide to evacuation strategies explains the options the file usually has to describe.
How the file fits with the rest of the application
The fire and emergency file is one of several documents regulation 4 requires with an application for a new higher-risk building. BSR reads them together. The fire strategy therefore has to agree with the drawings, the compliance statement and the plans for managing the build.
- Plans necessary to show that the work would comply with all applicable requirements of the building regulations.
- A competence declaration from the client.
- A construction control plan.
- A change control plan.
- A mandatory occurrence reporting plan, which BSR says should allow anyone on site to report risks such as the spread of fire or smoke.
- A Building Regulations compliance statement.
- The fire and emergency file.
- A partial completion strategy where part of the building is to be occupied before the whole is complete.
The compliance statement must set out the approach taken for each element of the building and the reasons for adopting it, with an explanation of why the approach is appropriate. BSR asks applicants to name the guidance, standards or design codes they intend to follow, why they chose them and how following them means the work will comply. The fire strategy is usually where that reasoning is made for Part B. The two documents should therefore say the same thing in the same terms.
In the competence declaration the client confirms it has taken all reasonable steps to check that the principal designer and principal contractor are competent. The guide to who writes a fire strategy covers what that means for the fire engineer. BSR also asks applicants to upload only the drawings that describe the project and show compliance, to refer to them throughout the application and to upload a reference file so its assessors can find the parts being relied on.
What BSR looks for in the fire safety content
BSR's page on getting applications right (opens in a new tab) says developers must clearly demonstrate how the design meets the building regulations, including the fire and structural requirements, with well-reasoned evidence and a clear compliance narrative. It says attaching hundreds of pages of drawings without context, which was not uncommon under the previous system, is no longer acceptable. A fire strategy that lists Approved Document B clauses and says the design complies is close to the kind of submission it describes.
BSR summarises what it wants as Identify, Clarify and Justify. Identify every aspect of the design within the scope of the building regulations, including the fire safety measures. Clarify which standards, codes or methods have been applied and why they suit this project. Justify the result with a clear narrative based on evidence. BSR's test for the level of detail is whether another professional unfamiliar with the project could read the application and understand how compliance has been shown.
For existing buildings BSR's guidance, in a section added on 1st April 2026, says applicants should avoid making assumptions. Where missing information makes an assumption unavoidable, the applicant must give evidence from surveys and inspections and describe how the assumption will be tested during construction. BSR also reminds applicants of their duties under the Regulatory Reform (Fire Safety) Order 2005.
In a page first published on 28th April 2025, BSR gave examples of fire safety failings it has seen. They include inadequate information on the fire resistance of cladding, walls or barriers, corridors too narrow for evacuation, smoke extraction that risked drawing smoke from a flat into the escape stair, gaps in sprinkler layouts and water supply capacity. One design provided no smoke detectors in the flats, only a heat detector in the kitchen. The guide to why Gateway 2 applications are rejected sets out BSR's published reasons and figures in full.
How the fire service is consulted
Regulation 6 (opens in a new tab) requires BSR to consult the fire and rescue authority before deciding an application. It must give the authority enough plans to show whether the work would comply with Part B. Those plans must include the fire and emergency file. The fire service therefore reads the strategy itself, not a summary of it.
BSR must not decide the application until 15 working days have passed from the start of the consultation. A longer period can be agreed in writing. If every consultee replies sooner, the bar lifts on the day after their views arrive. BSR need not consult at all where it is already satisfied there are enough grounds to reject the application.
Fire service comments carry weight. BSR's criteria for approving or rejecting applications (opens in a new tab) say unresolved concerns from statutory consultees, particularly fire and rescue services, should not be deferred through approval with requirements. BSR assesses applications in multi-disciplinary teams that include fire safety professionals. Its data for August to October 2026 records 115 fire service professionals among the 514 people from outside organisations who have been involved in its work.
The plan of fire service access and water supply is a required part of the file. It is sensible to settle it with the local fire service before submission. If the fire service raises a concern during the consultation that is still unresolved, BSR's criteria mean it should not be left to a requirement attached to the approval.
How long Gateway 2 takes and what it costs
The regulations set the decision periods. BSR's guidance adds that the time it takes depends on the quality of the application and the complexity of the work.
| Step | Period | Where it comes from |
|---|---|---|
| Decision on a valid application for a new higher-risk building | 12 weeks from receipt | Regulation 5, unless a longer period is agreed in writing |
| Decision on work to an existing higher-risk building | 8 weeks | Regulation 13, unless a longer period is agreed in writing |
| Each stage of a staged application | Up to 12 weeks | BSR guidance, unless an extension is agreed |
| Fire and rescue authority consultation | 15 working days | Regulation 6, unless a longer period is agreed in writing |
| Notice to BSR before work starts | At least 5 working days before | Regulation 9 |
| Notice to BSR after commencement | Within 5 working days | Regulation 9 |
| Approval lapses if work has not reached commencement | 3 years | BSR guidance |
BSR's published data (opens in a new tab) for the rolling 12 weeks to 1st November 2026 shows 42 decisions on new higher-risk buildings and conversions. Of these 40 were approvals and 2 were rejections, an approval rate of 95 percent that does not count invalidations and withdrawals. The median time to approval was 20 weeks. For complex cases it was 35 weeks.
BSR's strategic plan for 2026 to 2027 (opens in a new tab), published on 31st March 2026, says it expects by the end of March 2027 to respond to a Gateway 2 application for a new building in 18 weeks or less in non-complex cases. It also expects an approval rating of 65 percent. On a staged application for a single tower in two stages, BSR expects stage one to cover the foundations up to the ground floor slab or plinth.
Under the charging scheme for 2026 to 2027 (opens in a new tab), updated on 8th April 2026, the client pays £195 with the application and £156 per hour of BSR staff time, plus any costs of other authorities and third parties. Since 1st October 2026 applications for dwellings or purpose-built student bedspaces must also include building safety levy information. BSR says work creating 10 or more residential units is a major residential development and may require the levy to be paid.
What happens to the fire strategy after approval
BSR can approve, approve with requirements or reject. Regulation 7 (opens in a new tab) allows approval with requirements only with the applicant's written consent, for example that a document is provided within a set period or that work does not go beyond a set point until it is approved. An applicant who disagrees with a decision can ask for a review and then appeal to the First-tier Tribunal.
Once approved, the documents uploaded with the application become the agreed documents. The fire and emergency file is one of them. BSR's guidance says the work must comply with the agreed documents throughout the build. Any change to one is a controlled change. For a major change, work on that part of the project must stop until BSR approves the change. BSR's data to 1st November 2026 gives a median of 7 weeks to close major change requests on new build projects, which BSR describes as one week more than the statutory target.
The same file returns at completion. The completion certificate application must include the fire and emergency file. Its report must then demonstrate how compliance was achieved rather than how it is to be achieved. The guide to Gateway 3 covers that stage. A strategy written loosely at Gateway 2 tends to generate controlled changes during construction and a harder Gateway 3.
Does Gateway 2 apply in Wales and Scotland?
The BSR procedure described here applies in England only. In Wales the local authority is the building control authority for higher-risk buildings. There the fire and emergency file must expressly contain the proposed fire strategy under Schedule 1 paragraph 5(1)(d) of SI 2025/1321 (opens in a new tab), in force since 1st July 2026. The English Schedule 1 does not ask for it in those words. The guide to higher-risk buildings in Wales explains that regime. Scotland has no gateways. Building work there needs a building warrant from the council verifier.
If you have a higher-risk building heading for Gateway 2 in England, our Gateway 2 and Gateway 3 support service writes the fire and emergency file alongside the compliance narrative and checks it against the rest of the design package. Where the fire design is engineered rather than taken from guidance, our fire engineering service prepares the analysis behind it.
Sources
This guide was written from these official sources. Check the current version before relying on any figure.
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 4 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, Schedule 1 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 6 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 12 (official source, opens in a new tab)
- Building Control Approval for Higher-Risk Buildings (BSR guidance) (official source, opens in a new tab)
- Preparing Information for a Building Control Approval Application (BSR guidance) (official source, opens in a new tab)
- Getting Building Control Applications Right (BSR) (official source, opens in a new tab)
- Criteria for Validating, Approving or Rejecting Building Control Applications (BSR) (official source, opens in a new tab)
- BSR Building Control Approval Application Data, August to October 2026 (official source, opens in a new tab)
- Building Safety Regulator Strategic Plan 2026 to 2027 (official source, opens in a new tab)
- Building Safety Regulator Charging Scheme 2026 to 2027 (official source, opens in a new tab)
- Grenfell Tower Inquiry: Government Progress Report, September 2026 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025, Schedule 1 (official source, opens in a new tab)