What Gateway 3 is
Gateway 3 is the completion certificate stage for higher-risk building work in England. BSR describes it as completion approval, where the building must pass its checks before occupancy. BSR's guidance (opens in a new tab) says you must apply for a completion certificate when building work on a higher-risk building has been completed.
Under regulation 40 (opens in a new tab) of the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 the application must be made in writing to BSR and signed by the client. It is made through the same online service as the Gateway 2 application, using that application's reference. A certificate issued under regulation 44 is evidence that all applicable requirements of the building regulations have been met, though not conclusive evidence.
The overview of the three gateways explains how Gateway 3 relates to the earlier stages. What follows covers the evidence the application needs and the rules on occupation. Our Gateway 2 and Gateway 3 support service assembles the completion pack.
Who can move in and when
Section 76 (opens in a new tab) of the Building Safety Act 2022 applies to the construction of a higher-risk building, the creation of additional residential units in one and works that make a building higher-risk. If a residential unit is occupied before a completion certificate is issued for the relevant part of the building, the relevant Accountable Person commits an offence unless they have a reasonable excuse. A unit is occupied if there is a resident of it. BSR's own summary is that without its approval no resident can legally move in.
Section 77 (opens in a new tab) makes it an offence for the Principal Accountable Person if the building is occupied but not registered. BSR's guidance says a higher-risk building with at least 2 residential units must be registered before people live there and that a completion certificate is needed to register it. On conviction on indictment both offences carry up to two years' imprisonment, a fine or both. The registration offence adds a daily fine for each day the default continues after conviction.
Registration is a separate application by the Principal Accountable Person. The registration guidance (opens in a new tab) asks for a building summary including height, floors, residential units and date of completion, with the names and contact details of the Accountable Persons. The charge is £251 for each building. The guide to Accountable Persons and the golden thread explains those roles.
BSR's FAQ notes one exception. The offence of occupying part of a building without a completion certificate does not apply to building work in an existing hospital or care home. A completion certificate must still be applied for. BSR says nothing in building law stops that part of the building being used while it assesses the application.
What the application must include
Regulation 40 sets out the content of the application and the documents that must go with it. The application describes the work as built, including its location, the use of each storey, the height and number of storeys and the number of flats, residential rooms and commercial units. The client must state that to the best of its knowledge the work as built complies with all applicable requirements of the building regulations.
- A notice stating the date the building work was completed.
- A plan to a scale of not less than 1:1250 and any other plans needed to show the work complied.
- The agreed documents from Gateway 2: the construction control plan, change control plan, mandatory occurrence reporting plan, Building Regulations compliance statement and fire and emergency file.
- The change control log, updated to show every change.
- A compliance declaration from each principal designer and principal contractor confirming they fulfilled their Part 2A duties, with their dates of appointment.
- A statement signed by the client and the person receiving the building information confirming the handover under regulation 38.
- A levy liability statement where building safety levy information was required, a requirement added on 1st October 2026.
- Client confirmation where an agent makes the application.
If the client cannot obtain a compliance declaration, the application must include a statement from the client giving the reasons. BSR's guidance also asks for the latest version of the drawings and plans, any fire compliance statement for category B work, plans of any new drains and sewers and a summary of the completed work with its completion date.
BSR's page on Gateway 3 (opens in a new tab) puts the same list in practical terms. It names as-built drawings, fire and structural safety documentation, the golden thread of information, a declaration that the golden thread has been received by those responsible and evidence that design changes since Gateway 2 were properly assessed and managed.
The as-built fire and emergency file
The fire and emergency file submitted at Gateway 2 comes back at Gateway 3 with a different job. Schedule 1 (opens in a new tab) paragraph 5 requires its report, once the work is completed, to demonstrate how compliance with the regulations relating to building safety risks was achieved. At Gateway 2 it showed how compliance was to be achieved. The guide to the Gateway 2 fire strategy covers the file's original content.
In practice the as-built file is the approved strategy brought up to date with every controlled change made during construction. A well prepared file describes the products and systems actually installed, the fire service access and water supply as built and the management arrangements the owner is taking on. BSR says it will compare the original Gateway 2 documents with the updated ones and review the change log. A difference that the change control log does not explain is likely to draw questions.
The government's Grenfell Tower Inquiry progress report, updated on 2nd October 2026, records that Recommendation 10 would require a fire safety strategy by a registered fire engineer to be reviewed and resubmitted at Gateway 3. The government accepted it and gave its status as in progress. The law today asks for the as-built fire and emergency file.
Handing information to the Accountable Person
Regulation 38 (opens in a new tab) of the higher-risk procedures regulations requires the client to hand over two sets of information. The first is the fire safety information, together with ventilation, energy and overheating information where those parts of the regulations apply. The second is the specified golden thread information, which is a copy of the completion certificate application and every document that must go with it.
The information must be given no later than the date the work is completed. Where a partial completion certificate applies it must be given no later than the date the part is to be occupied. The golden thread information must keep its filing structure, indexes and keys and be in a format the recipient can read, keep and update.
The recipient is the Accountable Person for the part of the building concerned and any Responsible Person under the Fire Safety Order. Where the building is not a higher-risk building for the occupation regime after the work, it is the Responsible Person alone. The recipient must give the client a notice acknowledging receipt, confirming they can access the information and that it is enough to understand, operate and maintain the building and its fire safety systems.
Regulation 39 (opens in a new tab) defines fire safety information as information on the design and construction of the building and its services, fittings and equipment and on the materials used, which will help the Responsible Person operate and maintain the building with reasonable safety. Once the certificate is approved, the client must send the recipient a copy of the application, its documents and the certificate. The guide to Regulation 38 covers the equivalent duty for buildings outside the higher-risk regime.
How BSR decides a completion certificate application
BSR must decide a valid application within 8 weeks unless a longer period is agreed in writing. An application is valid if it complies with regulation 40. Before deciding, BSR must consult the fire and rescue authority and must arrange an inspection of the completed work.
| Step | Rule | Source |
|---|---|---|
| Decision period | 8 weeks from receipt of a valid application unless a longer period is agreed in writing | Regulation 41 |
| Fire and rescue authority consultation | 15 working days, with plans including the fire and emergency file | Regulation 42 |
| Inspection | BSR must inspect the completed work before deciding | Regulation 43 |
| Approval tests | Work complete and compliant, documents complete and accurate, handover information complete and provided | Regulation 44 |
| Building safety levy | Where a levy liability statement was required, the collecting authority must have agreed it, from 1st October 2026 | Regulation 44 |
| Charge for 2026 to 2027 | £234 with the application plus £156 per hour of BSR staff time and any costs of other authorities and third parties | BSR charging scheme |
Regulation 42 (opens in a new tab) applies the fire service consultation to HRB work, category A work and category B work where Part B applies. The plans sent must show whether the work as built complies with Part B. BSR need not consult where there are already enough grounds to reject.
BSR says it will assess the documents, compare the original documents with any updated ones, review the change log and changes submitted during the build and inspect the completed work. Under regulation 44 (opens in a new tab) it must approve if satisfied, after taking all reasonable steps, that the tests are met. Otherwise it must reject and give reasons. An applicant who disagrees can ask for a review and then appeal to the First-tier Tribunal.
Two money matters can hold up a certificate that is otherwise ready. BSR cannot issue it until the local council or other collecting authority confirms a notice of no charge or full payment of the building safety levy. BSR will also not issue it while charges on the building control approval application are overdue. The charges come from the charging scheme for 2026 to 2027 (opens in a new tab).
Partial completion and phased occupation
Regulation 45 (opens in a new tab) allows a partial completion certificate where part of a new higher-risk building is to be occupied before the whole is complete. It also covers parts of an existing one that are to be reoccupied. The application must show the part to be occupied and the location of the flats, describe the work that remains and include a partial occupation statement describing the stages and when each is expected to start. The same 8 week decision period applies.
BSR's guidance says a partial completion certificate can only be sought if a partial completion strategy was submitted with the Gateway 2 application and the request follows that strategy. Any building safety levy due for the completed stages must have been paid. A change to the strategy must be submitted to BSR.
This is a decision for the Gateway 2 stage. A developer who may want residents to move into part of the building early needs the partial completion strategy in the original application, with a fire strategy that works for each stage of occupation while construction continues nearby.
Gateway 3 so far and what has held it up
BSR's data for August to October 2026 (opens in a new tab) shows 42 Gateway 3 decisions in the rolling 12 weeks to 1st November 2026. Of these 31 were approved and 11 were invalidated. None was recorded as rejected. BSR says the 11 failed initial statutory validation checks, such as missing mandatory safety documentation. They were returned to the applicants. Most of the approvals, 24 of the 31, were internal refurbishments.
BSR says no new build project that has passed through Gateway 2 has reached Gateway 3 yet. Of the 379 Gateway 3 applications it has received, 288 are internal refurbishments. Most of the rest are transitional cases (44) and NHS internal refurbishments (28). There is therefore no published decision time yet for new buildings approved under the full regime.
BSR's Gateway 3 page, first published on 17th October 2025, lists the issues that slowed early applications. They are gaps in the fire and structural safety documentation, weak records of changes made after Gateway 2, as-built information that did not match the systems or materials installed and safety systems that passed tests on their own but did not work correctly together. The page recommends the practical steps below.
- Keep a clear and current golden thread of fire and structural safety information throughout the project.
- Engage early and consistently with registered building inspectors and BSR regulatory leads.
- Record every design or product change so decisions, approvals and as-built outcomes are linked.
- Run internal checks before submission so documents, calculations and test certificates agree.
- Treat safety evidence as a live record during construction rather than something compiled at the end.
These steps start long before completion. BSR's guidance on preparing a Gateway 2 application asks the construction control plan to describe how as-built evidence will be captured, with a list of the evidence expected. The principal contractor must keep the change control log that is submitted at Gateway 3.
BSR's criteria say approval with requirements at Gateway 2 should not be used to secure information that will be captured through the golden thread or Gateway 3. In its data to 1st November 2026 BSR also reported that inspections of new build projects had found a small amount of work that deviates from the designs agreed at Gateway 2. BSR said it will take a rigorous approach so that safety is not compromised.
In its strategic plan of 31st March 2026 BSR said it does not want safe buildings to stand empty because of administrative delays it causes. It committed to having the experts to review completed buildings, to publishing comprehensive guidance on making an application and to giving clear information where it must refuse a certificate so the necessary changes are understood.
After the certificate and outside England
Once the building is occupied the in-occupation regime takes over. Under section 79 of the Building Safety Act 2022 BSR can direct the Principal Accountable Person to apply for a building assessment certificate within 28 days. The guide to what a building safety case is covers that stage. The Gateway 3 information is the starting point for it.
Wales has its own completion and partial completion certificates in Part 5 of SI 2025/1321 (opens in a new tab), in force since 1st July 2026, with the council as building control authority and an 8 week decision period. Scotland has no Gateway 3. The completion certificate goes to the council verifier under section 17 (opens in a new tab) of the Building (Scotland) Act 2003.
For a higher-risk building in England, our Gateway 2 and Gateway 3 support service prepares the as-built evidence and the completion application. Our Regulation 38 fire safety information service prepares the handover pack the Accountable Person must acknowledge.
Sources
This guide was written from these official sources. Check the current version before relying on any figure.
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 40 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 38 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 44 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 45 (official source, opens in a new tab)
- Building Safety Act 2022, section 76 (official source, opens in a new tab)
- Building Safety Act 2022, section 77 (official source, opens in a new tab)
- Applying for a Completion Certificate (BSR guidance) (official source, opens in a new tab)
- Applying to Register a High-Rise Residential Building (official source, opens in a new tab)
- Gateway Three: The Final Safety Gate Before Occupation (BSR) (official source, opens in a new tab)
- BSR Building Control Approval Application Data, August to October 2026 (official source, opens in a new tab)
- Building Safety Regulator Charging Scheme 2026 to 2027 (official source, opens in a new tab)
- Building Safety Regulator Strategic Plan 2026 to 2027 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025 (official source, opens in a new tab)