Building control checks that the plans and fire strategy show the work will meet Part B. An English local authority must grant full plans unless the application is incomplete, lacks the detail needed or shows a contravention. The fire service is consulted on buildings the Fire Safety Order covers. Queries range from missing information to concern with the design approach.

Last reviewed
Reading time
13 minutes
Related service
Fire Strategy Reports
A modern building photographed in black and white

Who checks your fire strategy

Outside the higher-risk regime, building work in England is checked by a building control body. GOV.UK (opens in a new tab) says you can choose your local authority's building control department or a private registered building control approver. An approver tells the local authority about the work by giving an initial notice.

Building control approves the building work, not the fire strategy as a document. The strategy and the plans are the evidence that the work will meet Part B. Our fire strategy reports service writes strategies with that test in mind.

The people doing the checking are regulated. Checking plans submitted to a local authority is a restricted activity under the Building (Restricted Activities and Functions) (England) Regulations 2023 (opens in a new tab). The Building Safety Regulator says that after April 2024 it is a criminal offence to work as a building inspector without being registered. It says building control bodies should identify a non-standard building, such as one with high levels of complexity, before the project starts.

Higher-risk buildings follow a different route. In England the Building Safety Regulator is the building control authority for them and a registered building control approver cannot take the work. Our guide to the Gateway 2 fire strategy covers that regime.

Full plans, building notice or regularisation

On the local authority route there are three ways to apply. The table gives GOV.UK's description of each and what it means for fire safety.

Local authority application types in England
ApplicationWhat GOV.UK saysWhat it means for fire
Full plansThe most thorough option. A decision within 5 weeks or 2 months with your consentRequired for any building the Fire Safety Order covers. The fire strategy and plans go with the application
Building noticeOnly for smaller projects. Work can start 2 days after the notice is submitted. There is no formal approval as there is with full plansNot available for buildings the Fire Safety Order covers
RegularisationRetrospective approval for work already carried out without consent, from a local authority only. Only work carried out after 11th November 1985 can be approved this wayThe fire case still has to be made for the work as built

Regulation 12(3) (opens in a new tab) of the Building Regulations 2010 requires a full plans application for building work to a building the Regulatory Reform (Fire Safety) Order 2005 applies to now or will apply to after the work. The Welsh version of the regulation is the same. In practice that covers non-domestic buildings and blocks of flats.

On the approver route MHCLG said in April 2026 that there is no mandatory plan approval, although best practice may include informally approving plans. Its consultation Plan approval requirements for new builds and fire safety order buildings (opens in a new tab) ran from 2nd April 2026 to 11th June 2026. It proposed full plans for all new dwellings on the local authority route and mandatory plans certificates for new dwellings and Fire Safety Order buildings on the approver route. It also proposed changes to when the fire service is consulted.

GOV.UK says the feedback is being analysed. MHCLG stated an intent for the new dwelling rule to be in force by 1st October 2026 but regulation 12 read on 23rd November 2026 does not contain it.

What the application must show

Regulation 14 (opens in a new tab) sets out what a full plans application must include in England. Alongside the details of the applicant, client, principal contractor and principal designer, it must state whether the Fire Safety Order applies or will apply to the building. It also gives the use of each storey, the height and the number of storeys before and after the work.

Where Part B imposes a requirement four copies of the full plans are needed, unless the work relates only to a dwelling-house or flat. Full plans also include any other plans necessary to show that the work would comply. That brings the strategy and its drawings into the application. Our guide to fire strategy drawings explains what they show.

Fire services publish what they want to see. Cheshire Fire and Rescue Service's consultation guidance (opens in a new tab) says the package must identify which document has been used in the design, such as Approved Document B or BS 9999. It asks for legible scaled plans that clearly show the fire safety arrangements and site plans showing fire service access. For fire engineered schemes it asks for any fire strategy document, modelling reports with their input and output files and evidence that building control has assessed and agreed the analysis.

On substance, reviewers test the strategy against Part B and the guidance it relies on. These points come up most:

  • The strategy should name its basis of design. Approved Document B says that if another standard or guidance document is adopted, its relevant fire safety recommendations should be followed in their entirety.
  • Departures need a case. Where alternative methods are adopted the overall level of safety should not be lower than the approved document provides. It is for those undertaking the work to demonstrate compliance.
  • The evidence should match the risk. The government's FAQ warns that following Approved Document B may not be sufficient where the consequences of fire spread and fire induced structural failure are more significant.
  • Management assumptions must be realistic. Approved Document B says reliance on an unrealistic or unsustainable management regime cannot be considered to have met the requirements.
  • A change of use brings in B1, B2, B3, B4(2) and B5 in all cases under the England version of regulation 6, with B4(1) where the building exceeds 11 metres.

Agree the approach early. Approved Document B says that where there are other ways to comply, those carrying out the work should seek to agree this with the building control body at an early stage. For an alternative approach to B5 the FAQ (opens in a new tab) says it would be advisable to seek the advice of the fire and rescue service.

How building control decides

Under regulation 14A (opens in a new tab) the local authority must grant a full plans application unless it fails one of three tests. The application may not comply with the content rules in regulation 14. It may not be sufficiently detailed in any respect for the authority to decide whether the work would contravene an applicable requirement. Or it may show that the work would contravene one.

If the application is defective the authority may reject it or, only where the applicant has asked or consented in writing, grant it subject to modifications or further plans. A rejection must give its reasons. The authority must notify its decision within five weeks or a longer period agreed in writing. An applicant can appeal a rejection to the regulator within 21 relevant days under regulation 14B (opens in a new tab).

An approver works to a comparable standard. Regulation 4 of the 2024 approver regulations (opens in a new tab) requires it to take such steps as are reasonable to be satisfied, within the limits of professional skill and care, that the work complies. The provisions include the requirements for building work, the dutyholder and competence duties and Regulation 38.

How the fire service is consulted

Building control must consult the fire authority on Fire Safety Order buildings before it signs off the design. The duty now sits in the Building Regulations and the 2024 approver regulations. The rules differ by route.

Fire service consultation by building control route
RouteWhen the fire service is consultedTiming ruleLegal basis
Local authority, EnglandBefore determining a full plans application to erect, extend or structurally alter a Fire Safety Order building or change its use. Not needed where the authority is itself the enforcing authorityConsultation must happen before the decisionBuilding Regulations 2010, regulation 15A, from 1st October 2023
Registered building control approver, EnglandBefore or as soon as practicable after the initial notice and any relevant amendment notice, before a plans certificate and before a final certificateNo plans or final certificate until 15 working days after consulting, unless views arrive earlierBuilding (Registered Building Control Approvers etc.) (England) Regulations 2024, regulation 9, from 6th April 2024
Local authority, WalesBefore determining a full plans application to erect, extend or materially alter a Fire Safety Order building or change the use of all or part of oneNo approval until 15 days after consulting, unless views arrive earlierBuilding Regulations 2010, regulation 15B, from 1st July 2026
Building Safety Regulator, higher-risk buildings in EnglandBefore deciding, with plans that include the fire and emergency file15 working daysHigher-Risk Buildings Procedures Regulations 2023, regulation 6

An approver must give the fire authority sufficient plans to show whether the work would comply with Part B and must have regard to any views it expresses. MHCLG summarised the difference in its 2026 consultation. Approvers consult at four stages, while local authorities only consult when reviewing a full plans application.

Cheshire Fire and Rescue Service says consultations should not be sent where the building control body is not satisfied with the proposals. The package should include the building control body's own assessment and the fire safety conditions it proposes. The service aims to respond in writing within 15 working days, as the procedural guidance sets out. For complex or fire engineered schemes it considers an early consultation meeting, requested through the building control body, beneficial.

The consultation pro forma (opens in a new tab) building control sends asks for the principal design documents used, whether a performance based fire engineered solution is adopted and whether analysis such as CFD has been reviewed and by whom. Its list of supplied information gives a fire strategy as the first example. The form belongs to procedural guidance revised in July 2020, which an MHCLG circular of 15th July 2020 (opens in a new tab) recommends as good practice. That guidance predates regulation 15A, the 2024 approver regulations and the Welsh regulation 15B.

The operational standards rules

Building control bodies in England work to the Building Safety Regulator's operational standards rules (opens in a new tab). They are made under sections 58Z to 58Z10 of the Building Act 1984 and apply to local authorities and registered building control approvers alike. Both must comply and the Regulator may take action against those who fail to. The current version was updated on 22nd May 2026.

Several rules bear directly on how a fire strategy is handled:

  • Rule 1.5 requires records that show engagement with statutory consultees, the reasons for not accepting their views and that a relevant registered building inspector supports the decision.
  • Rule 3.3 requires the body to put in writing any non-compliance, the views of statutory consultees and any other conditions or recommendations when it assesses an application or gives a plans certificate.
  • Rules 3.4 and 3.5 require it to anticipate and fulfil consultation requirements and to tell consultees in writing whether it accepts their recommendations, with reasons.
  • Rules 3.7 to 3.12 set a risk-based inspection regime with reports for every inspection, recorded within 5 working days and given to the applicant as soon as possible.
  • Rules 4.3 and 4.4 require every contravention to be resolved before a completion or final certificate. An approver must cancel its initial notice as soon as possible where contraventions cannot be resolved.
  • Rule 1.7 requires records, including decisions on applications, to be kept for at least 15 years from the work completion date.

Rules 1.5 and 3.5 answer a common question. Building control makes the decision. Where it does not adopt the fire service's views it must record its reasons and tell the fire service in writing.

The Regulator monitors compliance through quarterly returns (opens in a new tab). They cover full plans applications assessed within 5 weeks, rejections for non-compliance and decisions made without fire service consultation or with no response. For projects identified as non-standard the target is a bespoke inspection schedule with additional critical inspection points on 90 percent of projects in year 1, rising to 92 percent and then 95 percent.

Common reasons for queries

The statutory reasons are the three in regulation 14A: an incomplete application, too little detail to decide and a design that shows a contravention. Behind those sit recurring technical problems.

The fullest published record comes from London Fire Brigade's Fire Engineering Group. Its quarterly fire engineering reports (opens in a new tab) covered January 2020 to March 2021. The series stopped after March 2021 and the figures relate only to consultations handled by that group in London.

In the first quarter of 2020 the group received 124 consultations, responded to 118 and issued a not satisfied response on 72 percent. The later reports, up to the quarter from 1st January to 31st March 2021, gave figures between 58 and 84 percent. The reasons ranged from insufficient information to a fundamental concern with the design approach. Recurring issues included:

  • single staircases serving mixed office and residential uses or continuing down to basements
  • a lack of consideration of disabled evacuation
  • CFD modelling that did not follow SCA guidance or used a soot yield that was not conservative
  • modern methods of construction not fully justified
  • schools assessed to BS 9999 rather than BB100, which the reports called the primary design guide
  • fit-out fire strategies that significantly altered key fire safety measures designed in the shell and core build
  • extensions above 18 metres without a firefighting shaft
  • omission of sprinklers

The Building Safety Regulator makes a similar point for higher-risk buildings. It says simply listing a standard is not enough and the application must explain its relevance and how it has been applied to the design. That is good practice on any project. A fire strategy review before submission tests these points before building control does.

Completion and Regulation 38

Building control's work does not end with the plans. Under regulation 17 (opens in a new tab) a local authority gives a completion certificate when, after taking all reasonable steps, it is satisfied the relevant provisions are met. Those include Schedule 1 and Regulation 38 fire safety information. It has eight weeks from receiving the completion notice and the certificate is evidence of compliance but not conclusive evidence.

Regulation 38 requires the person carrying out the work to tell the authority, usually within 5 days, that the fire safety information has been given to the Responsible Person and whether the acknowledgement was received. On the approver route the fire service is consulted again before the final certificate. Our guide to Regulation 38 covers the pack.

Changes during construction matter here. Where the design moves away from the approved strategy, the sensible course is to update the strategy and plans and agree the change with building control before the work is built. Every contravention has to be resolved before a completion or final certificate is given.

Wales and Scotland

In Wales the full plans rule for Fire Safety Order buildings is the same as in England. Since 1st July 2026 regulation 15B (opens in a new tab) has required the building control authority to consult the enforcing authority before deciding and not to grant approval until 15 days have passed unless views arrive earlier. The word working was removed from that period from 20th July 2026.

The Welsh Government publishes its own Operational Standards Rules (Wales) (opens in a new tab), which apply to local authorities and registered building control approvers. The Welsh Government says local authorities are the building control authority for higher-risk buildings in Wales and approvers cannot provide building control services for that work. Our Wales page covers projects there.

Scotland has no private route. The 32 local authorities are the only verifiers for building warrants in their own areas. Under regulation 11 of the Building (Procedure) (Scotland) Regulations 2004 (opens in a new tab) the verifier must consult the fire service on listed warrants, including non-domestic residential buildings and domestic buildings with a storey height over 18 metres. The Scottish Procedural Handbook says verifiers take account of consultees' opinions but are not bound to follow them. Our Scotland page covers projects there.

If building control has queried your strategy or you want it checked before submission, our fire strategy reports team can review the design and answer the queries. For higher-risk buildings our building safety gateway support covers the Gateway 2 application.

Sources

This guide was written from these official sources. Check the current version before relying on any figure.

Common questions

More on this topic.

All fire strategy questions

Building control approves the building work, not the strategy as a document. The strategy and plans are the evidence that the work meets Part B. A local authority must grant a full plans application unless it is incomplete, lacks the detail to decide or shows a contravention.

Keep reading

Related guides.

Talk to an engineer

Tell us about the building

Send us the drawings, the building type and the stage you are at. We reply the same day with a clear scope, programme and fixed fee.

  • 01Written in-house by the engineer who will defend it to the approver
  • 02Approved Document B, BS 9999, BS 9991 and BS 7974
  • 03Building Control and fire authority engagement handled for you
  • 04Projects of every size, across the UK

Request a quote

Same-day reply

Only used to reply to this enquiry.

We reply the same day.