What the three gateways are
The Building Safety Regulator (BSR) describes the Building Safety Act 2022 (opens in a new tab) as having three statutory gateways at its heart. The first is at planning, the second before construction and the last at completion.
The word gateway does not appear in the regulations. Gateway 1 is the planning fire statement and the statutory consultee duty. Gateways 2 and 3 are the building control approval and completion certificate procedures in the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 (opens in a new tab), in force from 1st October 2023. GOV.UK guidance uses those statutory terms while BSR's data and news use the gateway names.
The government's review of the higher-risk building definition (opens in a new tab), published on 17th December 2025, calls the regime's controls hard stops. The regulator must give approval before any building work on or to a higher-risk building can start. A new building can only be occupied once the regulator has approved the construction and certified that it meets the building regulations.
Both stops are backed by criminal law. GOV.UK says carrying out building work without the required building control approval is a criminal offence. Under section 76 of the Act (opens in a new tab) occupying a unit in a new higher-risk building before a completion certificate is issued is an offence by the relevant accountable person. The maximum on indictment is two years' imprisonment or a fine. Our building safety gateway support service prepares and manages Gateway 2 and Gateway 3 applications.
Which buildings go through which gateway?
The gateways do not all use the same test. Gateway 1 applies to a relevant building under article 9A of the Development Management Procedure Order 2015 (opens in a new tab). That means 18 metres or 7 storeys with two or more dwellings or educational accommodation. Gateways 2 and 3 apply to higher-risk buildings. GOV.UK describes these as buildings with at least 7 storeys or at least 18 metres that have at least 2 residential units or are a hospital or a care home.
Hospitals and care homes are therefore outside Gateway 1 but go through Gateways 2 and 3. Our guide to what is a higher-risk building explains how height and storeys are measured, when attached blocks count as one building and which buildings are excluded.
Under section 91ZA of the Building Act 1984 (opens in a new tab) BSR is the building control authority for any higher-risk building in England or any proposed one. That includes work that makes a building a higher-risk building or causes it to stop being one. The section has been fully in force since 1st October 2023. GOV.UK tells applicants not to apply to BSR for non-higher-risk buildings. Building control for those is managed by local authorities or businesses registered as building control approvers.
BSR became a standalone body on 27th January 2026 under SI 2026/20 (opens in a new tab). It is now an arm's-length body under the Ministry of Housing, Communities and Local Government (MHCLG) and no longer part of the Health and Safety Executive.
Gateways 1, 2 and 3 at a glance
The three gateways differ in stage, decision maker, scope and time limit. The charges shown are from BSR's 2026 to 2027 charging scheme.
| Point | Gateway 1 | Gateway 2 | Gateway 3 |
|---|---|---|---|
| Stage | Planning application | Before building work starts | When building work is complete |
| Law | Development Management Procedure Order 2015, article 9A | SI 2023/909 | SI 2023/909 and Building Safety Act 2022, section 76 |
| Who submits | The developer, with the planning application | The client | The client |
| Who decides | The local planning authority, with BSR as statutory consultee | BSR | BSR |
| Buildings | 18 metres or 7 storeys with two or more dwellings or educational accommodation | Higher-risk buildings, including hospitals and care homes | Higher-risk buildings, including hospitals and care homes |
| Statutory period | 21 calendar days for the consultee response | 12 weeks for a new building and 8 weeks for work to an existing one | 8 weeks |
| BSR charge | None in BSR's charging scheme. BSR says its pre-application advice is currently free of charge | £195 application charge plus £156 per hour | £234 application charge plus £156 per hour |
| Possible outcomes | A planning decision by the authority, which decides what weight to give BSR's advice | Approved, approved with requirements or rejected | A completion certificate or a rejection |
For a new building the 12 weeks begin with the date BSR receives the application. The period can be longer if BSR and the applicant agree in writing. Where all three gateways apply, each builds on the one before. The fire statement fixes the main fire safety decisions, Gateway 2 tests the full design against the building regulations and Gateway 3 tests what was built against what was approved.
Gateway 1: fire safety at planning
Since 1st August 2021 a planning application for a relevant building in England must be accompanied by a fire statement. It sets out the fire safety design principles, concepts and standards applied to the development. The duty came from SI 2021/746 (opens in a new tab). The government form has 16 sections, including the building schedule, the evacuation approach, the fire service site plan, access, appliance siting and water supply.
BSR has been the statutory consultee since 27th January 2026, taking over from the Health and Safety Executive. It has 21 calendar days to respond. The local planning authority considers BSR's advice and decides what weight to give it. BSR says its pre-application advice on Gateway 1 is currently free of charge.
Gateway 1 fixes decisions that are costly to change later, such as the number of stairs, firefighting shafts and fire appliance access. Our guide to the Gateway 1 fire statement covers the form, the exemptions and the concerns BSR raises most often. Our planning fire statements service prepares it.
Gateway 2: approval before work starts
GOV.UK's building control approval guidance (opens in a new tab), last updated on 1st October 2026, says the client must make sure approval is granted before any building work starts. The client must also make sure the information in the application is correct. The client can nominate someone to apply but the legal responsibility for the application stays with the client.
BSR's golden thread guidance (opens in a new tab) lists the documents in a Gateway 2 application.
- Drawings and plans
- A competence declaration
- A construction control plan
- A change control plan and log
- A building regulations compliance statement
- A fire and emergency file
- Client authorisation
- A site location plan
- A mandatory occurrence reporting plan
- A planning statement
- A partial completion strategy
Regulation 7 (opens in a new tab) says BSR must grant approval unless the application fails the requirements of regulation 4 or is not detailed enough for BSR to decide whether the work would contravene an applicable requirement. The same applies where the application shows the work would contravene a requirement or where the strategies for controlled changes, mandatory occurrence reporting, competence or the golden thread would contravene the regulations.
There are three outcomes: approved, approved with requirements and rejected. Approval with requirements needs the applicant's written consent. Work must not start on the parts subject to a requirement until BSR is satisfied.
Work to an existing higher-risk building falls into category A or category B. Category A includes changes to height, width, storeys, internal layout or the number of units. It also includes work to passive or active fire safety measures, staircases or escape routes and common parts, including internal or external remediation work. Everything else is category B. GOV.UK warns that an application under the wrong category is likely to be rejected.
Before deciding, BSR must consult the Fire Safety Order enforcing authority and the plans it sends must include the fire and emergency file. Under regulation 6 (opens in a new tab) it must not decide until 15 working days after consultation starts unless all consultees reply sooner. Our guide to the Gateway 2 fire strategy covers the fire and emergency file. Our guide to why Gateway 2 applications are rejected covers the reasons BSR has published.
Between the gateways: notices and change control
GOV.UK sets out the notices the client must give once approval is granted.
- A notice of intention to start work at least 5 working days before starting.
- A notice of commencement within 5 working days of reaching commencement.
- Notifications at the points set in the inspection schedule.
Approval lapses if commencement, as defined in regulation 46A of the Building Regulations 2010, is not reached within 3 years. Inspections during construction are charged at the hourly rate only.
Documents approved at Gateway 2 become agreed documents. Any change to them is a controlled change and must be recorded in the change control log. A major change needs a change control application. Building work must stop on that part of the project until BSR approves the change.
Under regulation 22 (opens in a new tab) BSR must determine a change control application within 6 weeks. BSR's data at 1st November 2026 showed 242 live major change requests. The median closure time for new build major changes was 7 weeks, which BSR describes as just one week more than the statutory target. The charging scheme also sets a £116 charge for a notifiable change.
Applications can be staged on single and multiple tower projects. No building work may start on a stage until the application for that stage is approved. Emergency repairs need no prior approval. BSR must be told by the end of the first working day after the repair work starts and a regularisation certificate must then be applied for.
Gateway 3: the completion certificate
When building work is complete the client must apply for a completion certificate. GOV.UK's completion certificate guidance (opens in a new tab) says BSR will assess the information and documents and compare the original documents with any updated ones. It will review the change log and carry out an inspection of the completed work. Under regulation 41 (opens in a new tab) BSR must decide within 8 weeks.
The application uploads the latest agreed versions of the Gateway 2 documents, including the fire and emergency file. It adds drainage information, compliance declarations signed by each principal designer and principal contractor, a client confirmation statement and the change control log. It also includes a signed statement that building information has been handed to the responsible person and the principal accountable person.
BSR approves where the work complies with the applicable building regulations, the documents are complete and accurate and the information has been handed over. It issues a certificate only once it has confirmation that any building safety levy due has been paid. Partial completion is possible only where a partial completion strategy was submitted with the Gateway 2 application and only in line with it.
Under regulation 38 (opens in a new tab) the client must give the BFLO information and the specified golden thread information to the accountable person and any responsible person no later than the date the work is completed. The BFLO information includes the Regulation 38 fire safety information. The recipient must confirm they can access it and that it is sufficient to understand, operate and maintain the building and its fire safety systems.
A higher-risk building with at least 2 residential units must then be registered with BSR before people live there. A completion certificate is needed to register it. Our guide to Gateway 3 covers the completion evidence in detail.
Fees and how long the gateways take
Most BSR charges are a fixed amount with the application plus £156 per hour worked by BSR staff and any costs to BSR of relevant authorities and third parties. The client pays the design and construction charges, the person asking for a review pays for it and the Principal Accountable Person pays for registration. These figures are from the 2026 to 2027 charging scheme (opens in a new tab), updated on 8th April 2026. Charges are set each year.
| Charge | Fixed amount | Notes |
|---|---|---|
| Gateway 2 building control approval application (Schedule 1) | £195 | Plus £156 per hour of BSR staff time |
| Notification of a notifiable change (Schedule 8) | £116 | Plus £156 per hour |
| Change control application for a major change (Schedule 9) | £195 | Plus £156 per hour |
| Inspections during construction (Schedule 6) | No fixed amount | £156 per hour |
| Completion or partial completion certificate application, Gateway 3 (Schedule 10) | £234 | Plus £156 per hour |
| Regularisation certificate application (Schedule 11) | £156 | Plus £156 per hour |
| Request for review of a prescribed decision, such as a rejection at Gateway 2 or Gateway 3 (Schedule 26) | £312 | Plus £156 per hour. Refunded if the review finds for the applicant |
| Application to register a higher-risk building (Schedule 14) | £251 | Per building, paid by the Principal Accountable Person. No hourly charge |
The hourly element depends on how long BSR spends on a case. The exemption from charges for building work solely required to facilitate or improve a building's use by disabled persons has been extended to BSR.
The statutory periods are not the times applicants currently see. BSR's building control data for August to October 2026 (opens in a new tab) was first published on 6th November 2026 and corrected on 11th November 2026, with figures at 1st November 2026. Over a rolling 12 weeks new build Gateway 2 saw 42 decisions, of which 40 were approvals and 2 rejections. That is a 95 percent approval rate with a median approval time of 20 weeks. Complex cases are tracked separately with a median of 35 weeks.
External remediation applications had a 93 percent approval rate and a median of 32 weeks. Internal works under category A and B had a 91 percent approval rate and a median of 30 weeks. Across all categories 1,687 Gateway 2 applications were in progress. BSR says no new build projects that have passed through Gateway 2 have reached Gateway 3.
BSR's criteria page (opens in a new tab) sets expectations for requests for information. Responses should be received within 48 hours, even if only as a holding response. A request not answered within 1 working week is treated as a nil response. If a second request is not met the application is likely to be rejected.
BSR changes since June 2025, Wales and Scotland
BSR's operation has changed several times since mid 2025, as government and BSR announcements record.
- 30th June 2025: the government announced reforms (opens in a new tab) including a new Fast Track Process, over 100 new staff and a new MHCLG board to take on BSR functions as initial steps towards a single construction regulator.
- 27th January 2026: BSR became a standalone body, a move BSR says is underpinned by a significant operational reset of its role as building control authority.
- 1st April 2026: GOV.UK guidance added checks to make before applying for work to an existing higher-risk building and added remediation work to category A.
- 8th April 2026: a remediation improvement plan (opens in a new tab) with a dedicated external remediation team, a recruitment drive to bring regulatory lead caseloads down from an average of 25 to around 10, wider use of approval with requirements and monthly Gateway 2 data.
- 1st October 2026: the building safety levy came into effect. Work creating 10 or more residential units may need to pay it and completion certificates are withheld until the levy is paid or a notice of no charge is issued.
- 11th November 2026: the latest data release. New build applications rose from 17 in July to 64 in September, which BSR attributes to applicants submitting ahead of the levy.
The April 2026 plan aims by December 2026 to cut average decision times for remediation applications to under 12 weeks, with approval rates over 65 percent. It also aimed for a steady remediation caseload of 80 to 100 cases by 30th September 2026. At 1st November 2026 BSR reported 292 remediation applications in progress.
These gateways apply in England. Wales has its own procedures regulations, SI 2025/1321 (opens in a new tab), in force from 1st July 2026. Local authorities are the building control authority for higher-risk buildings there. Approval is decided within 12 weeks for a new building and 8 weeks for an existing one, with completion certificates within 8 weeks. Wales has no planning fire statement and fire and rescue authorities are statutory planning consultees instead. Our guide to higher-risk buildings in Wales covers that regime.
Scotland has no gateways. Parts 2 to 5 of the Building Safety Act 2022 extend to England and Wales only. Work in Scotland needs a building warrant before it starts and acceptance of a completion certificate by the council verifier at the end. Our Scotland page covers projects there.
Our building safety gateway support service can take a project through Gateway 2, change control and Gateway 3.
Sources
This guide was written from these official sources. Check the current version before relying on any figure.
- Building Act 1984, section 91ZA (official source, opens in a new tab)
- Building Safety Act 2022, section 76 (official source, opens in a new tab)
- Development Management Procedure Order 2015, article 9A (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 5 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 7 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 22 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 41 (official source, opens in a new tab)
- Building Control Approval for Higher-Risk Buildings (BSR) (official source, opens in a new tab)
- Applying for a Completion Certificate (BSR) (official source, opens in a new tab)
- Building Safety Regulator Charging Scheme 2026 to 2027 (official source, opens in a new tab)
- Building Safety Regulator Building Control Approval Application Data, August to October 2026 (official source, opens in a new tab)
- BSR Becomes Standalone Body (27th January 2026) (official source, opens in a new tab)
- Gateway Three: The Final Safety Gate Before Occupation (BSR) (official source, opens in a new tab)