Two definitions for two phases
England has two legal definitions of a higher-risk building and they apply at different stages of a building's life. The design and construction definition is in section 120D of the Building Act 1984 (opens in a new tab), not in the Building Safety Act itself. Section 31 of the Building Safety Act 2022 inserted it and it has been in force since 28th June 2022.
The occupation definition is in section 65 of the Building Safety Act 2022 (opens in a new tab). Both cover buildings in England that are at least 18 metres in height or have at least 7 storeys. Section 120D adds uses specified in regulations and section 65 requires at least 2 residential units.
The detail sits in the Higher-Risk Buildings (Descriptions and Supplementary Provisions) Regulations 2023 (opens in a new tab), SI 2023/275, in force since 6th April 2023. Its Explanatory Note says the 1984 Act covers their design and building work to them and the 2022 Act covers safety management once they are occupied. Regulation 3 applies the same rules on what a building is, how height is measured and how storeys are counted to both definitions.
Government guidance sets three criteria to consider together: use, the legal definition of a building and height and storeys. Our building safety gateway support service starts by testing a project against all three. Separate guidance covers new buildings (opens in a new tab) and the occupation phase (opens in a new tab). Both say you may wish to seek legal advice.
| Point | Design and construction | Occupation |
|---|---|---|
| Law | Building Act 1984, section 120D | Building Safety Act 2022, section 65 |
| Height or storeys | At least 18 metres or at least 7 storeys | At least 18 metres or at least 7 storeys |
| Uses | At least two residential units, a care home or a hospital | At least two residential units |
| Hospitals and care homes | Included | Excluded |
| Independent sections | Not used while the building is being constructed or proposed | Each independent section is treated as a building |
| What it governs | Building control by the Building Safety Regulator, Gateways 2 and 3 | Registration and the duties of Accountable Persons |
Which uses bring a building into scope?
For design and construction, regulation 2 of SI 2023/275 specifies three descriptions: a building which contains at least two residential units, a care home and a hospital. For occupation, section 65 needs at least two residential units. Section 115 (opens in a new tab) of the Act defines a residential unit as a dwelling or any other unit of living accommodation.
The guidance gives examples of a residential unit. They include a flat, a studio flat, a home of multiple occupation, a bedroom with shared kitchen and bathroom in university halls and a unit within a supported accommodation building. Privately owned, private rented and social rented units are all residential units. The uses below are in scope where the height or storey threshold is met.
- Mixed use buildings, such as a shopping centre with two or more residential units.
- Boarding accommodation in schools and university accommodation.
- Supported and sheltered housing, such as domestic abuse refuges, children's homes and supported or sheltered homes for older people and those with additional care needs.
- Short-term lets, such as a property let online.
- Serviced apartments, which the guidance says do not fall within the meaning of hotel.
The occupation guidance adds that supported or sheltered homes count where they do not fall within the definition of a care home. In high-rise residential and mixed schemes a small residential element can bring a whole building into the regime. Take a hypothetical 20 metre office building with two flats on its top floor. It contains at least two residential units, meets the height test and is not excluded. It is a higher-risk building in both phases.
Are hospitals and care homes higher-risk buildings?
Hospitals and care homes are higher-risk buildings for design and construction if they meet the height or storey test. They are not higher-risk buildings for the occupation regime. The Explanatory Note to SI 2023/275 says care homes and hospitals are excluded from the definition in the 2022 Act but not from the definition in the 1984 Act.
The regulations define both terms. A care home is a care home within the meaning of section 3 of the Care Standards Act 2000. A hospital is a hospital within the meaning of section 275 of the National Health Service Act 2006 that has at least one bed intended for a person admitted for an overnight stay. The guidance says a general practitioner surgery that does not allow overnight stays would not meet the definition.
The review of the definition (opens in a new tab) published on 17th December 2025 explains the split. Hospitals and care homes were brought into the design and construction regime because of the higher likelihood of vulnerability of their users. They were left out of the occupation regime because the Regulatory Reform (Fire Safety) Order 2005 already applies to them and many of the new duties were not relevant to them.
A tall hospital or care home project therefore goes to the Building Safety Regulator (BSR) for building control approval but is not registered once occupied. Our healthcare and hospitals page covers fire strategy work in that sector.
How height is measured
A building needs to meet either the height threshold or the storey threshold, not both. Regulation 5 (opens in a new tab) and regulation 1(3) of SI 2023/275 set the method.
- Height is measured from ground level to the top of the floor surface of the top storey, ignoring any roof-top machinery or plant storey.
- Where the ground is uniform, ground level is the surface of the ground immediately adjacent to the building.
- Where the ground is not uniform, ground level is the lowest part of the surface of the ground adjacent to the building.
- Where the top storey is not directly above the lowest part of the adjacent ground, height is measured vertically from that lowest point to a horizontal projection from the top of the top storey's floor surface.
- The guidance says it is unlikely to be appropriate to use lightwells to identify ground level.
The new building guidance says its method should be used rather than methods set out in other documents. A change to the occupation guidance on 19th October 2023 clarified that other methods or guidance cannot be used. A height taken from a fire strategy written to Approved Document B should be checked against these rules. A building close to either line deserves a measured survey and a note of how ground level was taken.
For registration BSR asks for height in metres to two decimal places from ground level to the top floor, not the roof. It allows an estimate where the building has at least 7 floors or is clearly over 18 metres, as long as you keep a record.
How storeys are counted
Regulation 6 (opens in a new tab) sets three kinds of storey that are ignored. Every other storey counts.
- Any storey below ground level. A storey is below ground if any part of the finished surface of its ceiling is below the ground level immediately adjacent to that part of the building.
- Any roof-top storey that is a machinery or plant area or consists only of roof-top machinery or plant rooms.
- A gallery whose internal floor area is less than 50 percent of the internal floor area of the largest storey vertically above or below it that is not below ground level.
The guidance says that if floor 3 of a 7-storey building contained only plant rooms and machinery, it should still be counted as a storey. For an independent section on a podium in an occupied building, any storey directly beneath it that is not below ground level counts.
A storey must be fully enclosed to count. The guidance says the roof should not be counted as a separate storey and open rooftops such as rooftop gardens are not considered storeys.
All three criteria guides carry a government notice, updated on 28th May 2025, about a First-tier Tribunal decision dated 3rd July 2024 on roof gardens being considered a storey. The notice says the department has considered the Tribunal's views and recognises the need for clarity in the legislation. It is consulting BSR and other relevant stakeholders on a proposal to amend SI 2023/275 to make clear that roof gardens should not be considered a storey. In the meantime its view remains that roof gardens are not storeys. At 23rd November 2026 legislation.gov.uk showed no amendment to regulation 6.
On sloping sites the guidance counts from the lowest part of the ground that touches the building to the highest point of the overall attached structures. Its Diagram 9 shows a 4-storey tower attached to an 8-storey tower on sloping ground and counts the building as 8 storeys.
What counts as one building?
Regulation 4 (opens in a new tab) says a structure that is not attached to any other structure is a building. Where two or more structures are attached, that set of structures is a building. A structure is a roofed construction with walls.
During design and construction the whole set of attached structures is one building. Regulation 4(5) switches off the independent section rules while a building is being constructed or proposed. The guidance says this holds even when one or more attached structures do not meet the height, storey or use criteria. Its diagrams treat towers joined by a shared car park, walkways, a party wall or shared foundations as one building.
Once occupied, each independent section is treated as a building. An independent section has access for people to enter and leave the wider building that can be reached from anywhere in the section. It either has no access to any other section or only has access to a section that contains no residential unit. Openings intended for exceptional use, including emergency use or maintenance, do not count as access. The guidance shows two towers that share only a party wall and a basement car park, each with its own entrance, as separate independent sections. Any plant room serving a section is part of it and the guidance adds that a plant room may be part of more than one independent section.
BSR's criteria for validating, approving or rejecting applications (opens in a new tab) says attached means structurally attached and the provision of services does not constitute structural attachment. Submitting a single application for multiple higher-risk buildings would be grounds for rejection. A podium scheme can therefore be one building during construction and several buildings in occupation, each tested on its own.
Which buildings are excluded?
Some buildings are excluded even when they meet the height and use tests. The current text is in regulation 7(2) (opens in a new tab) for design and construction and regulation 8(2) (opens in a new tab) for occupation. Both were substituted from 16th January 2024 by SI 2024/41. An exclusion applies only where the building consists entirely of the excluded use.
| A building consisting entirely of | Design and construction | Occupation |
|---|---|---|
| A care home | Not excluded | Excluded |
| A hospital | Not excluded | Excluded |
| A secure residential institution | Excluded | Excluded |
| A hotel | Excluded | Excluded |
| Military barracks | Excluded | Excluded |
| Living accommodation provided by the Ministry of Defence | Excluded | Excluded |
| Living accommodation for His Majesty's forces or a visiting force, international headquarters or defence organisation | Excluded | Excluded |
A secure residential institution includes a prison, young offenders institution, detention centre or secure local authority accommodation. Hotels provide overnight accommodation for customers staying for leisure or business, hostels of that kind count as hotels and hotels are excluded regardless of how long they are occupied.
The new building criteria guidance, last updated on 28th May 2025, still quotes the Ministry of Defence exclusion as it stood before 16th January 2024. Under the current law a building used for both residential and non-residential purposes is excluded only where all of its living accommodation is provided by the Ministry of Defence.
The registration guidance tells you not to register a building entirely used as a hospital, care home, secure residential institution, hotel, military premises or prison. The higher-risk definitions do not amend others, such as the relevant building test for leaseholder protections in section 117 of the Act.
Registration and what follows occupation
A higher-risk building must be registered with BSR before people live there. The registration guidance (opens in a new tab) says the Principal Accountable Person must make sure it is registered. Under section 77 (opens in a new tab) the Principal Accountable Person commits an offence if the building is occupied but not registered, with a maximum on indictment of two years' imprisonment or a fine.
A new building must have a completion certificate or final certificate before it is registered. Under section 76 (opens in a new tab) occupying a unit in a new higher-risk building before a completion certificate is issued is an offence by the relevant accountable person.
The application asks for the following.
- The building name, address and postcode.
- A building summary including height in metres, number of floors and residential units and completion date.
- The names and contact details of the Principal Accountable Person and the Accountable Persons.
- A card payment of the registration application charge, which Schedule 14 of the 2026 to 2027 charging scheme (opens in a new tab) sets at £251 per building.
The Principal Accountable Person must then give BSR key building information within 28 days of applying and report changes within 28 days of becoming aware of them under the Key Building Information Regulations (opens in a new tab). It covers matters such as fire and smoke controls, structure, staircases, external walls and later building work. BSR says much of it can come from the most recent fire risk assessment or an EWS appraisal and you should not need a full separate survey.
Changes to the building summary, the Principal Accountable Person, the Accountable Persons or their parts must be reported within 14 days and changes to structure or fire safety information within 28 days. A refused registration can be reviewed if you ask within 21 days of the decision, excluding public holidays. Schedule 26 of the charging scheme sets the charge for reviewing a decision not to register at £312 with the request plus £156 per hour of BSR staff time. The registration guidance, last updated on 25th March 2025, still gives £302.
Our guides to Accountable Persons and the golden thread and the building safety case cover the occupation duties that follow.
Gateway 1, the review of the definition, Wales and Scotland
Planning uses a different test. A relevant building under article 9A of the Development Management Procedure Order 2015 (opens in a new tab) is 18 metres or 7 storeys and contains two or more dwellings or educational accommodation. Care homes are not dwellings for that test. A tall hospital or care home is therefore not a relevant building for the Gateway 1 fire statement but is a higher-risk building at Gateways 2 and 3. Our guide to the Building Safety Act gateways sets out all three.
The definition is under ongoing review. MHCLG asked BSR to review it after Grenfell Tower Inquiry recommendation 113.7, which called a definition based on height alone essentially arbitrary. BSR concluded the review in February 2025 and its findings were published on 17th December 2025. It found insufficient evidence to suggest changes should be made and concluded it would not be right either to increase or to decrease the scope now. BSR will operate an ongoing review of the definition. The review also explains that the 7 storey test was added in response to stakeholder concerns that a threshold based only on height could be gamed.
Both definitions cover buildings in England only. Wales has its own design and construction definition covering 18 metres or 7 storeys with at least one residential unit, a hospital, a care home or a children's home. Our guide to higher-risk buildings in Wales covers that regime.
Scotland has no higher-risk building regime under the Building Safety Act 2022, which extends to England and Wales only with listed exceptions. Since 1st April 2026 Scottish verifiers have used a Compliance Plan Approach, which is guidance only, for high risk buildings. Our Scotland page covers projects there.
Our building safety gateway support service can test a scheme against these rules before its height, layout and uses are fixed.
Sources
This guide was written from these official sources. Check the current version before relying on any figure.
- Building Act 1984, section 120D (official source, opens in a new tab)
- Building Safety Act 2022, section 65 (official source, opens in a new tab)
- Higher-Risk Buildings (Descriptions and Supplementary Provisions) Regulations 2023, Explanatory Note (official source, opens in a new tab)
- Higher-Risk Buildings (Descriptions and Supplementary Provisions) Regulations 2023, regulation 6 (official source, opens in a new tab)
- Higher-Risk Buildings (Descriptions and Supplementary Provisions) Regulations 2023, regulation 7 (official source, opens in a new tab)
- Criteria for Determining Whether a New Building Is a Higher-Risk Building (official source, opens in a new tab)
- Criteria for Being a Higher-Risk Building During the Occupation Phase (official source, opens in a new tab)
- Applying to Register a High-Rise Residential Building (BSR) (official source, opens in a new tab)
- Definition of Higher-Risk Buildings: Initial Review and Plans for Ongoing Review (official source, opens in a new tab)
- Building Safety Regulator Charging Scheme 2026 to 2027 (official source, opens in a new tab)
- Building Safety Act 2022, section 76 (official source, opens in a new tab)