Why a fire strategy falls out of date
A fire strategy describes a building at a point in time. Each later fit-out, new partition, replacement door, service penetration or change in how the building is used moves the real building further from that description. The strategy is only useful to the Responsible Person and the fire risk assessor while the two still match. Our fire strategy review service finds and closes that gap.
Outside change control on higher-risk buildings, no law says in terms that a fire strategy must be updated. Several duties still force a fresh look whenever a building is altered.
- The Building Regulations rules on material alterations and material changes of use
- Regulation 38 handover where Part B applies to an extension or a relevant change of use
- For higher-risk buildings in England, Building Safety Regulator approval before work starts and change control for the agreed documents, including the fire and emergency file
- The Fire Safety Order duty to review the fire risk assessment
If any of them applies, the fire strategy is the natural place to explain the building after the work. It is best revised while the work is designed.
What makes an alteration material
Regulation 3 of the Building Regulations 2010 (opens in a new tab) lists what counts as building work. It includes the erection or extension of a building, its material alteration and work required on a material change of use. The regulation applies in England and Wales.
An alteration is material if the work would at any stage leave the building not complying with a relevant requirement where it previously did. It is also material if a building that did not comply before becomes more unsatisfactory against that requirement. The relevant fire requirements are B1 (means of warning and escape), B3 (internal fire spread, structure), B4 (external fire spread) and B5 (access and facilities for the fire service). Part A, Part M and, in England since 1st October 2024, Part T are also relevant requirements, while B2 on internal linings is not.
The government's Manual to the Building Regulations (opens in a new tab), a code of practice for England, says an alteration is material if it would make a building less safe structurally, more at risk from fire or less accessible for disabled people. After the work, regulation 4 (opens in a new tab) requires the altered building to comply or, where it did not comply before, to be no more unsatisfactory than it was.
The Home Office guide to fire safety in purpose-built blocks of flats (opens in a new tab) says proposed alterations must be considered against the current Building Regulations, not the rules the building was built to. The Building Regulations do not require existing fire safety measures to be upgraded, although existing non-compliances must not be made any worse.
The same guide advises that proposals to alter fire alarm systems, means of escape, smoke control, structure or fire service facilities should go to a building control body to decide whether approval is needed. Material alterations to blocks of flats, including work inside individual flats, need building control approval or an offence is committed.
Designing the alteration and revising the strategy
Approved Document B Volume 1 (opens in a new tab) gives examples of what an alteration can trigger in dwellings. A fire detection and alarm system should be installed where a new habitable room is provided above or below the ground storey. The same applies to a new habitable room at ground storey without a final exit. Where windows are replaced, cavity barriers may be needed around the opening.
For buildings the Fire Safety Order covers in England, regulation 15A (opens in a new tab) requires the relevant authority to consult the enforcing authority under the Order before deciding a full plans application to erect, extend or structurally alter the building or change its use. In most cases that is the local fire and rescue authority. The consultation is a good reason to submit the revised strategy with the application.
Approved Document B warns that guidance written for assessing existing buildings is unlikely to be appropriate for building work the regulations control. Its 2026 amendments on second staircases and evacuation lifts in blocks of flats took effect on 30th September 2026. The earlier guidance continues to apply where a building notice, initial notice or full plans application was submitted before that date and the work is sufficiently progressed within 18 months, which for work to an existing building means when that work has started. A revised strategy should state which version of the guidance the new work follows.
| Change | Why it matters | What to revise |
|---|---|---|
| New partitions and fit-outs | Can lengthen escape routes, create inner rooms or breach compartment lines | Escape route plans, travel distances and compartmentation drawings |
| Replacing flat entrance or escape route doors | The Home Office flats guide calls replacing a self-closing, fire-resisting flat entrance door with one that lacks either quality a common contravention | Door schedule and fire door plan |
| Fire alarm or smoke control changes | The Home Office advises sending these to building control to decide whether approval is needed | System descriptions, cause and effect and the Regulation 38 records |
| Extensions or a change of use | Regulation 38 applies where Part B imposes a requirement. Regulation 6 applies Part B to a change of use, as our change of use guide explains | The whole strategy, including evacuation and fire service access |
Regulation 38 after later work
Regulation 38 (opens in a new tab) applies to later work as well as new buildings. In England it applies where Part B imposes a requirement on the work and the work either consists of or includes the erection or extension of a relevant building or is carried out in connection with a relevant change of use. A relevant building is one the Fire Safety Order applies to or will apply to after the work. A relevant change of use is a material change of use after which the Order will apply or continue to apply.
The handover steps are the same as for a new building. In England since 1st October 2023 the Responsible Person must acknowledge that the information is sufficient to understand, operate and maintain the building and its fire safety systems after the work. The person carrying out the work then notifies the relevant authority, usually within 5 days of the handover deadline. Our guide to Regulation 38 sets out the other notice periods and what belongs in the pack.
For a complex building, the information Approved Document B describes includes a detailed record of the fire safety strategy. On an extension the clearest record is a revised strategy covering the whole building as it now stands. Regulation 38 does not list material alterations on their own. Check other work against its wording with the building control body.
Higher-risk buildings: approval before work starts
Regulation 11 of the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 (opens in a new tab) requires the client to apply for and be granted building control approval from the Building Safety Regulator, meet any pre-start requirements and notify the start date before any work to an existing higher-risk building. The Regulations apply in England only and have been in force since 1st October 2023.
The Regulator's guidance on building control approval (opens in a new tab) says approval is needed unless the work consists only of exempt work, competent person scheme work, fibre optic cabling work or emergency repairs. It is also needed for work that makes an existing building a higher-risk building or stops it being one. Carrying out building work without the required approval is a criminal offence and the client stays legally responsible for the application even if someone else submits it.
Applications fall into two categories under regulation 12 (opens in a new tab). The Regulator says an application made under the wrong category is likely to be rejected.
| Point | Category A work | Category B work |
|---|---|---|
| What it covers | Work that changes the height, width, number of storeys, number of flats or residential rooms, stairs, escape routes or internal layout. Also work to the external wall and work affecting passive or active fire safety measures or the common parts | Any work that does not fall within category A |
| Fire information | A fire and emergency file, with a competence declaration, construction control plan, change control plan, mandatory occurrence reporting plan and Building Regulations compliance statement | Where Part B applies, fire safety compliance information setting out the fire safety design principles, concepts and standards with plans showing how the work meets Part B |
| Further documents | A partial completion strategy where part of the building is to be occupied before the work is complete | The Regulator may require any category A document, including a fire and emergency file, before deciding |
| Decision period | 8 weeks from receipt unless a longer period is agreed in writing | 8 weeks from receipt unless a longer period is agreed in writing |
Before applying, the Regulator's guidance tells applicants to consider their duties under other legislation such as the Fire Safety Order and to complete surveys, inspections or building information checks. The application must explain how the effect of the work was assessed and how the work will comply. Where missing information makes assumptions unavoidable, they must be backed by survey evidence and the application must say how they will be tested during construction. The strategy therefore has to describe the building as found as well as the new work.
Change control and the agreed documents
Once approval is granted, change control applies. Regulation 18 (opens in a new tab) covers any change to the current plans, to a stage of the work or to the strategies, policies or procedures in an agreed document. Before any such change the client must make sure a record is made and a revised version of each affected agreed document is produced. Changes fall into three classes set by regulation 26 (opens in a new tab) and explained in the Regulator's guidance on making changes to a higher-risk building project (opens in a new tab).
| Class | Examples | What must happen |
|---|---|---|
| Major change | A material change of use of any part, a change to height, width or storeys, to the number or width of stairs or escape routes, to the external wall, to active or passive fire safety measures referred to in the fire and emergency file, to the common parts or to design assumptions in the compliance statement | Stop related work, apply for change control and wait for approval. The Regulator has up to 6 weeks to decide unless an extension is agreed |
| Notifiable change | A change to the layout of a flat that does not affect the common parts, to the number or size of openings for pipes, ducts or cables and any other change to the fire and emergency file | The client notifies the Regulator in writing with the revised agreed document before the change is made. Any further information requested must be given within 10 working days |
| Recordable change | A controlled change that is neither major nor notifiable, such as a swap within the same design specification | Record it in the change control log |
The principal contractor must keep a change control log under regulation 19 (opens in a new tab), recording each change, its class, the advice sought and the agreed document revised. Do not bundle unrelated changes. The Regulator says that if one change in a combined notification or application is rejected, all of them are rejected.
At completion, regulation 38 of the 2023 Regulations requires the client to give the fire safety information and the specified golden thread information to the accountable person and any responsible person. Our guide to Accountable Persons and the golden thread covers what happens to it next.
Reviewing the fire risk assessment after works
The fire risk assessment review applies to every building the Fire Safety Order covers, whatever the size of the job. Article 9(3) (opens in a new tab) requires the Responsible Person to review the assessment regularly and particularly where there is reason to suspect it is no longer valid or there has been a significant change, including significant changes, extensions or conversions of the premises. Any changes the review shows are needed must be made and the review must be recorded.
The Home Office guide for persons with duties (opens in a new tab) says you should arrange a review if you suspect the assessment is no longer valid. Its examples are significant changes to the premises, the occupants or the management and a fire in the premises. It also says compartmentation should be checked particularly after works that might penetrate or damage it. A review does not necessarily mean a completely new assessment, as our guide to fire strategy and fire risk assessment explains.
In England the Fire Safety (England) Regulations 2022 (opens in a new tab) add update duties for blocks of flats. In high-rise residential buildings the floor plans and building plan must be updated as soon as reasonably practicable after changes. The external wall record must be revised after significant changes to the external walls and sent again to the fire and rescue service. Fire safety instructions to residents must be re-issued after material changes.
Enforcement and common mistakes
Under section 36 of the Building Act 1984 (opens in a new tab) a notice requiring removal or alteration of non-compliant work cannot be given more than 10 years after the work was completed. The Building Safety Act 2022 substituted that period in England from 2023 and in Wales in full from 1st July 2026. Contravening the building regulations is an offence under section 35 (opens in a new tab) and on indictment can lead to up to two years' imprisonment, a fine or both.
The Home Office flats guide was first written in 2011 and its statements on enforcement time limits are out of date. Official guidance names these common mistakes.
- Treating minor works as harmless. The Home Office says removing cross-corridor fire doors or replacing a fire door within a flat by a non-fire-resisting door would normally contravene the Building Regulations
- Starting work on a major change before the Regulator approves it
- Relying on assumptions about an existing building without survey evidence
- Designing new work to guidance written for assessing existing buildings
A simple routine helps. Keep the strategy under version control with a revision history and the version of the guidance it follows. Check each new project against it before design starts. At completion issue a revised strategy or a clear addendum with the fire safety information and give it to the fire risk assessor.
Wales and Scotland
In Wales regulations 3 to 5 of the Building Regulations 2010 also apply, while regulation 6 and Regulation 38 have separate Welsh versions. The Welsh higher-risk buildings regime under the Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025 (opens in a new tab) has applied since 1st July 2026, with the council as building control authority. Its rules on changes during the work are outside the scope of this page. Our Wales page covers projects there.
In Scotland the Building Regulations 2010 and the Higher-Risk Buildings Procedures Regulations do not apply. Alterations and conversions need a building warrant under the Building (Scotland) Act 2003 and the Building (Scotland) Regulations 2004. The fire risk assessment is reviewed under Part 3 of the Fire (Scotland) Act 2005 (opens in a new tab). Our Scotland page covers projects there.
If a building has been altered since its strategy was written, a fire strategy review will show where the document and the building no longer match. Where no usable strategy survives, our guide to retrospective fire strategies explains the alternative. For new work, our fire strategy reports team can produce the revised strategy and our Regulation 38 service compiles the handover pack.
Sources
This guide was written from these official sources. Check the current version before relying on any figure.
- Building Regulations 2010, regulation 3 (official source, opens in a new tab)
- Building Regulations 2010, regulation 4 (official source, opens in a new tab)
- Building Regulations 2010, regulation 38 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 11 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 12 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 18 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 26 (official source, opens in a new tab)
- Building control approval for higher-risk buildings (Building Safety Regulator) (official source, opens in a new tab)
- Making changes to a higher-risk building project (Building Safety Regulator) (official source, opens in a new tab)
- Regulatory Reform (Fire Safety) Order 2005, article 9 (official source, opens in a new tab)
- Fire safety in purpose-built blocks of flats (Home Office guide) (official source, opens in a new tab)
- Manual to the Building Regulations, July 2020 (official source, opens in a new tab)
- Approved Document B Volume 1: Dwellings (England) (official source, opens in a new tab)
- Building Act 1984, section 36 (official source, opens in a new tab)