What a fire strategy is
A fire strategy sets out how a building is designed, built and managed to be safe from fire. It explains the means of escape, the compartmentation, the structural fire resistance, the detection and alarm, any smoke control and the access and facilities for the fire service. Most importantly it explains how those measures are meant to work together and what the design assumes about how the building will be run.
It is the thinking behind every fire safety decision on the drawings. An architect uses it to fix stair positions and door ratings. A services engineer uses it to set the alarm and smoke control logic. Building control uses it to test the design and the person who later runs the building uses it as the baseline for the fire risk assessment. Our fire strategy reports service produces this document at whatever stage a project has reached.
There is no single agreed definition. Imperial College London's estates team notes in its contractor guidance that the term has never been formally defined in scientific, legislative or technical literature. It separates retrospective, design and as-built fire strategies. In plain terms a design strategy is written before construction, an as-built strategy records what was actually provided and a retrospective strategy is written for an existing building that never had one or has lost it.
Is a fire strategy a legal requirement?
We have found no Act or regulation in England that defines a fire strategy. The government has also confirmed that one is not a required application document. In its Grenfell Tower Inquiry progress report (opens in a new tab) of September 2026, updated on 2nd October 2026, it corrected its own earlier response and stated that a fire safety strategy is not a required document to be submitted as part of an application. It added that the higher-risk regime does already require extensive information on fire safety.
That may change. Inquiry Recommendation 10 asks for a statutory requirement that a fire safety strategy produced by a registered fire engineer be submitted with building control applications for higher-risk buildings at Gateway 2 and reviewed and resubmitted at completion at Gateway 3. The government has accepted it and the report gives its status as In progress. The government says that requiring a fire engineer to produce the strategy depends on progress with Recommendations 15, 16 and 18, which aim to increase fire engineering capacity.
So the honest answer for 2026 is that a fire strategy is not a statutory document in England. In practice building control bodies and fire services usually expect one. The fire service consultation pro forma gives the fire strategy as the first example of supplied information. The next section explains why.
Why a strategy is written anyway
The duties that make a strategy necessary in practice sit in three places. Each one asks for information that a fire strategy is the natural place to hold.
- Building control has to be satisfied that the work meets Part B of the Building Regulations. The approved documents are only one way to comply and those carrying out the work must demonstrate compliance if they take another route. A strategy is how that case is made.
- Regulation 38 requires fire safety information to be handed to the Responsible Person by completion. Approved Document B says that where a fire safety strategy has been prepared it should be made available to the relevant dutyholder. For complex buildings it asks for a detailed record of the fire safety strategy itself.
- For a higher-risk building in England, the Gateway 2 application to the Building Safety Regulator must include a fire and emergency file. The Regulator's guidance says the fire and emergency file is often known as a fire strategy. For category B work a fire compliance statement may be needed instead, which the same guidance says may also be known as a fire strategy for the work.
Regulation 38 applies in England and Wales, in a separate version for each nation. A building with no strategy usually reaches handover with no clear record of what its fire safety depends on. That is why a strategy written early saves time later.
The fire and emergency file is set out in Schedule 1 of the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 (opens in a new tab). It must cover the matters considered when assessing the building safety risks, the design approach taken to comply and the measures the owner should adopt to manage the building so anyone in it can be safely evacuated, including assumptions about the occupiers and their likely behaviour. It must also include a plan of the fire and rescue service requirements for access and water supply and a report showing how compliance is to be achieved.
The five Part B requirements a strategy answers
Part B of Schedule 1 to the Building Regulations 2010 (opens in a new tab) sets five functional requirements. They say what must be achieved, not how. A fire strategy takes each one in turn and explains how this building meets it.
| Requirement | What the law asks for | What the strategy shows |
|---|---|---|
| B1 Means of warning and escape | Appropriate provision for early warning of fire and appropriate means of escape to a place of safety outside the building | The alarm and detection, the evacuation strategy, travel distances, exit widths, stairs, refuges and how disabled people leave |
| B2 Internal fire spread (linings) | Internal linings that adequately resist the spread of flame and have a reasonable rate of heat release or fire growth | The lining classifications for rooms, corridors and escape routes |
| B3 Internal fire spread (structure) | Stability for a reasonable period, fire resisting separation, automatic fire suppression where necessary and restricted unseen spread in concealed spaces | The fire resistance of the structure, compartment lines, cavity barriers and any suppression |
| B4 External fire spread | External walls and roofs that adequately resist the spread of fire over them and from one building to another | The external wall construction, space separation and roof coverings |
| B5 Access and facilities for the fire service | Reasonable facilities to assist firefighters and reasonable access for fire appliances within the site | Vehicle access, firefighting shafts, fire mains, water supplies and any firefighting lifts |
Approved Document B (opens in a new tab) also covers regulations 6(3), 7(2) and 38. Its plain summary of regulation 38 is to provide fire safety information to building owners. Volume 1 deals with dwellings, including blocks of flats. Volume 2 deals with all other buildings.
The guidance changes often. The current England volumes are the 2019 edition incorporating the 2020, 2022, 2025 and 2026 amendments, collated with further amendments that take effect on 2nd September 2029. The 2026 amendments took effect on 30th September 2026 and provide for more than one common stair in blocks of flats with a storey 18m or more in height, with an 18 month transition for work notified before that date that is started and sufficiently progressed in time. A strategy should always state which edition it was written to.
Codes, guides and fire engineering
Approved Document B says it sets out what, in ordinary circumstances, may be accepted as one way to comply. Following it does not guarantee compliance and other routes should be agreed with the building control body early. If another standard is adopted, its fire safety recommendations should be followed in their entirety. Picking the easier clauses from two documents is not an acceptable design.
For some building types Approved Document B points elsewhere. It says Building Bulletin 100 should be used for schools (see our BB100 guide), the health department's Firecode should be followed for health care and the prison service's own design guide applies to prisons. It refers to annexes of BS 9999 for shopping complexes, assembly buildings and atria.
Where no code fits, fire safety engineering may provide an alternative approach. Approved Document B says it may be the only practical way to achieve a satisfactory standard of fire safety in some complex buildings and buildings with mixed uses, with BS 7974 and its published documents giving the framework. Our guide to fire engineered solutions explains how that route is argued and checked.
Whatever the route, the strategy must be realistic about management. Approved Document B states that reliance on an unrealistic or unsustainable management regime cannot be considered to have met the requirements. A design that only works if a fire warden is always present has to say so. The building owner then has to be able to deliver it.
Who checks the strategy
The building control body decides whether the design complies. For a higher-risk building in England that body is the Building Safety Regulator. The fire and rescue service is consulted on the plans before a decision is made.
The legal basis for that consultation has moved. Article 45 of the Fire Safety Order 2005 (opens in a new tab), which used to require it, was omitted in England on 1st October 2023 and in Wales on 1st July 2026. The duty now sits in the Building Regulations and, for higher-risk buildings in England, in the Higher-Risk Buildings Procedures Regulations.
| Building | Who consults | Legal basis | Notes |
|---|---|---|---|
| Buildings in England the Fire Safety Order applies to or will apply to, on a full plans application | The relevant authority that receives the full plans application | Building Regulations 2010, regulation 15A, from 1st October 2023 | Covers erection, extension, structural alteration and change of use. Not needed where the authority is itself the enforcing authority |
| Higher-risk buildings in England at Gateway 2 | The Building Safety Regulator, with the fire and emergency file | Higher-Risk Buildings Procedures Regulations 2023, regulation 6 | The application cannot be decided until 15 working days after consultation starts. A longer period can be agreed in writing |
| Buildings in Wales the Fire Safety Order applies to or will apply to, on a full plans application | The building control authority | Building Regulations 2010, regulation 15B, from 1st July 2026 | Covers erection, extension, material alteration and change of use. Approval cannot be granted until 15 days have passed unless the fire authority's views are received earlier |
The Regulator must decide a valid Gateway 2 application for a new higher-risk building within 12 weeks and for work to an existing one within 8 weeks, unless a longer period is agreed in writing. Its guidance warns that unresolved concerns from statutory consultees, particularly fire and rescue services, should not be deferred through approval with requirements. A strategy that leaves a fire service question open can stop the application.
The Regulator has also said that early submissions often fell short because critical fire and structural elements were unclear, undocumented or assumed rather than substantiated. Simply listing a standard is not enough. The strategy has to explain why that standard is relevant and how it has been applied.
Fire strategy or fire risk assessment?
They are different documents with different legal bases. The fire risk assessment is a duty under article 9 of the Fire Safety Order, which applies in England and Wales. The responsible person must make a suitable and sufficient assessment of the risks, review it regularly and keep a record of it. The fire strategy is a design document produced when a building is designed, extended, refurbished or changed in use.
The two are linked. Approved Document B says the aim of Regulation 38 is achieved when the person responsible for the building has the information to understand and implement the fire safety strategy, maintain the fire safety systems and carry out an effective fire risk assessment. The strategy says what should be there. The fire risk assessment checks what is there, that it works and that it still suits how the building is used.
The government has consulted on making that link explicit in England. Its review of Approved Document B ran from 25th March 2026 to 1st July 2026 and proposed text asking dutyholders to consider the fire risk assessment when scoping work to existing buildings. The aim was for the fire strategy, fire safety management plan and fire risk assessment to form a coherent set of measures. That is a proposal only and the outcome had not been published at the time of writing.
Who can write a fire strategy?
No law names who may write one. In England, regulation 11F of the Building Regulations has required since 1st October 2023 that anyone carrying out design work has the skills, knowledge, experience and behaviours needed for the design to comply. A firm must have the organisational capability to do so. Approved Document B adds that anyone using it should have sufficient knowledge and skills to apply it correctly and that suitably qualified and experienced professionals should be engaged where necessary.
The Inquiry wants this to go further. Recommendation 10 would require a registered fire engineer to produce the strategy for higher-risk buildings. Recommendation 15, to regulate the fire engineering profession, is also In progress and the government has set up a Fire Engineers Transitional Board. The Inquiry's Recommendation 8, quoted in the same report, says that calculating the likely rate of fire spread and the time needed for evacuation are matters for a qualified fire engineer.
In practice the right author depends on the building. A small extension designed to Approved Document B needs someone who knows that document well. A tall residential block, a hospital or a building with an engineered solution usually needs fire engineering input. Asking for a fire strategy review before submission is a sensible check when the author's experience is unclear.
Wales and Scotland
Wales has its own Approved Document B, published by the Welsh Government for use in Wales. Its Volume 2 says that for larger buildings a more detailed record of the fire safety strategy and the procedures for operating and maintaining fire protection measures will be necessary. Since 1st July 2026 Wales has also had its own higher-risk buildings procedures regulations, which include a fire and emergency file. Fire service consultation there now sits under regulation 15B. Our Wales page covers projects there.
Scotland uses different law. Its Technical Handbooks set the guidance, with Section 2 Fire revised for building warrant applications made on or after 6th April 2026. The non-domestic handbook says the objectives of any fire safety strategy should be established first and that the strategy should preferably support any fire safety risk assessment required under the Fire (Scotland) Act 2005. Since October 2013 a Fire Safety Design Summary has been required with the completion certificate for a new non-domestic building or a conversion to one. See our Scotland page for more.
If you are starting a project and are unsure what the strategy needs to cover, our fire strategy report example sets out a contents page built from the official lists. When you are ready to commission one, our fire strategy report team can quote from your drawings.
Sources
This guide was written from these official sources. Check the current version before relying on any figure.
- Grenfell Tower Inquiry: government progress report, September 2026, the construction industry (official source, opens in a new tab)
- Building Regulations 2010, Schedule 1 (official source, opens in a new tab)
- Building Regulations 2010, regulation 15A (official source, opens in a new tab)
- Building Regulations 2010, regulation 15B (Wales) (official source, opens in a new tab)
- Building Regulations 2010, regulation 11F (official source, opens in a new tab)
- Approved Document B: fire safety (GOV.UK collection page) (official source, opens in a new tab)
- Approved Document B Volume 2, 2019 edition incorporating 2020, 2022, 2025 and 2026 amendments (official source, opens in a new tab)
- Approved Document B 2026 amendments (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, Schedule 1 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 6 (official source, opens in a new tab)
- Preparing information for a building control approval application (Building Safety Regulator) (official source, opens in a new tab)
- Getting building control applications right (Building Safety Regulator) (official source, opens in a new tab)
- Criteria for validating, approving or rejecting building control applications (Building Safety Regulator) (official source, opens in a new tab)
- Regulatory Reform (Fire Safety) Order 2005, article 45 (official source, opens in a new tab)
- Regulatory Reform (Fire Safety) Order 2005, article 9 (official source, opens in a new tab)
- Review of Approved Document B: fire safety guidance (consultation, 2026) (official source, opens in a new tab)
- Approved Document B: fire safety (Welsh Government) (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025 (official source, opens in a new tab)
- Building Standards Technical Handbook, Non-domestic, April 2026 (Scottish Government) (official source, opens in a new tab)
- Building Standards Procedural Handbook, third edition (Scottish Government) (official source, opens in a new tab)
- Fire strategy, Imperial College London contractor portal (official source, opens in a new tab)