What the second staircase rule says
In England, Approved Document B Volume 1 (opens in a new tab) paragraph 3.30 says flats should be served by more than one common stair if either of two conditions applies. The first is that the flat is on a storey that does not meet the criteria for a single escape route or a small single stair building. The second is that the building has a top storey of 18 metres or more in height.
Condition (b) is the new one. It came in through the 2026 amendment booklet (opens in a new tab), which describes two changes. One is a new recommendation for more than one common stair in blocks of flats with a storey 18 metres or more in height. The other is a set of building design provisions to support the use of evacuation lifts in blocks of flats.
Approved Document B is guidance on meeting the Building Regulations 2010. The government's circular 01/2024 (opens in a new tab) says the changes apply only to buildings and building work in England. Its circular letter (opens in a new tab) went to building control bodies and the Building Safety Regulator.
The number of stairs is the first decision in a residential core and the hardest to change later. It belongs in the fire strategy from the first massing study, before floor plates and unit mixes are fixed.
Where the 18 metre line falls
Paragraph 3.30(b) refers to Diagram D6 in Appendix D. The height is measured from the upper floor surface of the top floor to ground level on the lowest side of the building. Roof-top plant areas and any top storeys consisting exclusively of plant rooms are excluded.
The wording is 18 metres or more. A top storey at exactly 18 metres is caught. Diagram 3.7 note 6 says the same from the other direction. A single common stair arrangement is only suitable for use in buildings with a top storey less than 18 metres in height.
Below 18 metres a single stair is not automatic. Paragraph 3.30(a) still calls for more than one common stair at any height where the single escape route and small single stair criteria in paragraphs 3.27 and 3.32 are not met. Among its conditions, paragraph 3.32 limits a small single stair building to a top storey of no more than 11 metres and no more than three storeys above the ground storey.
Dates and transitional arrangements
The amendment was published on 29th March 2024. The government's press release (opens in a new tab) of that day said it would apply from 30th September 2026. The booklet was updated in September 2024 to amend the guidance as it stands after the 2025 amendments. Its effective date, its 18 month transition and its stair provisions did not change.
The consultation response (opens in a new tab) describes the transition in two stages. It says the arrangements "will give developers 30 months from the publication of the guidance, during which new building regulations applications can conform to either the previous guidance or the updated guidance requiring a second staircase." It goes on: "When those 30 months have elapsed, all applications will need to conform to the new guidance. Any approved applications that do not follow the new guidance will have 18 months for construction to commence in earnest." If construction does not commence in earnest in that time, the response says a new building regulations application following the new guidance will be needed.
| Date | Stage |
|---|---|
| 23rd December 2022 to 17th March 2023 | Consultation on a 30 metre threshold, which drew 285 responses |
| 29th March 2024 | Amendment published. The 30 month window opens, during which applications could follow either version |
| September 2024 | Booklet updated with the same effective date, transition and stair provisions |
| 30th September 2026 | Amendment takes effect in England. The 18 month period for work under earlier applications to be sufficiently progressed begins |
| 1st October 2026 | The circular letter says all new applications will need to conform to the new guidance from this date |
The booklet sets out the mechanics. The previous guidance continues to apply where a building notice, an initial notice or a building control approval application with full plans was given to the relevant authority before 30th September 2026. In addition the work must have started and be sufficiently progressed either before that day or within the period of 18 months beginning on that day.
Sufficiently progressed has a set meaning. For a new building it is when the pouring of concrete for the permanent placement of the trench, pad or raft foundations has started. The start of permanent piling also counts. For work to an existing building it is when that work has started. For a material change of use it is when work to effect the change of use has started.
An approval alone does not keep a single stair scheme under the old guidance. A new building with an application in before 30th September 2026 still needs its foundation concrete or piling under way before that day or within the 18 month period. At the time of writing, in November 2026, that period is running. Programme the start on site with that in mind. Keep a dated record of when the concrete pour or piling began.
Why the threshold is 18 metres
The government first consulted on a higher threshold. It proposed that residential buildings above 30 metres should be designed and built with two staircases. Of the 285 responses, 186 (65 percent) agreed there should be a maximum height for a single stair. Only 72 (25 percent) agreed with 30 metres and 138 (48 percent) disagreed.
Asked for a preferred height, 72 respondents chose 30 metres, 60 chose 18 metres and 28 chose 11 metres. Another 14 wanted no threshold and 7 chose 50 metres.
The response says respondents supported 18 metres because it aligns with the higher-risk building threshold under the Building Safety Act, the Fire Safety Act, the baseline trigger recommendation for two stairs in the draft BS 9991 and the threshold for internal firefighting provisions. Taking this into account, the government decided to proceed with 18 metres for new tall residential buildings. It says the change will, for the first time in England, set a maximum height for using a single staircase in residential buildings.
The higher-risk building test is set in separate legislation. Check each test on its own terms. Our guide to higher-risk buildings explains how that one works.
Designing two stairs that count as two
A second stair only adds resilience if one fire cannot affect both. The amendment also restructured Section 3, separating the provisions for horizontal and vertical escape in a similar structure to Volume 2. These are the points that most affect a two stair core.
- Interlocked stairs, also called scissor or stacked stairs, should be considered a single escape route and do not constitute an alternative means of escape (paragraph 3.31).
- An escape route should not pass through one stair enclosure to reach an alternative exit. It may pass through a protected lobby of at least REI 30 of one stair (paragraph 3.37).
- A protected lobby should not provide direct access to more than one stair (paragraph 3.37).
- A common corridor connecting two or more storey exits should be divided by a self-closing fire doorset of at least E 30 Sa, positioned so that smoke does not affect access to more than one stair (paragraph 3.39).
- A common stair in a building with a storey 18 metres or more in height should be at least 1100 millimetres wide, as for a firefighting stair (paragraph 3.63).
- The corridor or lobby directly in front of each storey exit should have a smoke vent, as high as practicable, with its top edge at least as high as the stair door (paragraph 3.54).
A single escape route from the flat entrance door can still be acceptable on a storey. Paragraph 3.27 allows it where one common stair serves the storey and every flat is separated from the stair by a protected lobby or common protected corridor within the one direction travel distance. It also allows a flat in a dead end on a storey served by two or more stairs, within the same distance. Table 3.1 gives 7.5 metres in one direction and 30 metres in more than one direction. The one direction figure falls to 4.5 metres in a small single stair building.
Scissor stairs are the common trap. Two stairs wound around each other in one core save floor area but count as one route. A scheme over 18 metres that relied on them needs a genuinely separate second stair.
Does the amendment require evacuation lifts?
It does not. The response says the updated guidance will not call for evacuation lifts as a matter of course. What the amendment does is set design rules for lifts that are provided.
Under paragraph 3.29, where evacuation lifts are provided they should be located within an evacuation shaft containing a protected stairway, an evacuation lift and an evacuation lift lobby. The lobby should provide a refuge area for people waiting for the lift and have direct access to a protected stairway. It should not be directly accessible from any flat, maisonette, storage room or electrical equipment room.
Paragraph 3.53 adds that evacuation shafts should be given the same minimum protection as the stairway. Any smoke control system designed to protect the stair should extend the same level of protection to the evacuation lift and its lobby. New key terms define the evacuation shaft, the evacuation lift lobby and the interlocked stair. The definition of a storey exit now includes an evacuation lift lobby within an evacuation shaft.
Paragraph 3.105 now allows a lift serving a basement or enclosed car park to sit within an evacuation shaft as well as a protected stairway. The response also says a firefighting shaft is still expected alongside the protected stairs, with compliance with all other provisions of Approved Document B. London has its own planning policy on evacuation lifts, covered in our guide to London Plan Policy D5(B5).
The 2026 proposal for two evacuation lifts
A further change is being considered. The Building Safety Regulator's consultation on its review of Approved Document B (opens in a new tab), published with MHCLG, opened on 25th March 2026 and closed on 1st July 2026. It proposed that the guidance call for a minimum of two stairs and two evacuation lifts in all new residential buildings above 18 metres. Where a firefighting lift is already provided, that lift could have a dual function.
Its preferred option was a threshold of 18 metres. It put the cost uplift in the range of 0.1 to 0.2 percent of total build cost. The government's Grenfell progress report of September 2026 (opens in a new tab) says more than 500 responses were received and recommendations are expected by March 2027.
This is a proposal, not current guidance. Designs today follow paragraph 3.29, which sets rules for evacuation lifts where they are provided. On a scheme still in design, it is sensible to test early whether the cores could take two evacuation lifts in case the proposal is taken forward.
Existing buildings and the higher-risk regime
The amendment is guidance for building work. Its transitional wording covers new buildings, work to existing buildings and material changes of use. No official statement on GOV.UK, checked in November 2026, explains how it applies to an upward extension that takes a building to 18 metres or more. The response says there is no suggestion that existing and upcoming single staircase buildings are inherently unsafe as long as they have been built in accordance with the relevant standards, well maintained and properly managed. The March 2024 press release says existing tall buildings are also being considered as part of the Grenfell Tower Inquiry's recommendations.
A second stair changes the options in an emergency. The response says it will facilitate evacuation if a stay put recommendation needs to be overridden. Our guide to evacuation strategies covers stay put and simultaneous evacuation.
Buildings caught by the rule will often also be higher-risk buildings. The response says the fire safety design for any higher-risk building above 18 metres will be reviewed at Planning Gateway One by fire safety professionals and by a multi-disciplinary team at Gateway Two. Our building safety gateway support service covers both stages.
Second stairs in Wales and Scotland
The three nations are at different points. England has had the rule since 30th September 2026, Scotland since 1st October 2019 and Wales has not adopted one.
| Nation | Position | Since |
|---|---|---|
| England | More than one common stair where the top storey is 18 metres or more (Approved Document B Volume 1 paragraph 3.30(b)) | 30th September 2026, with transition |
| Wales | No 18 metre threshold in the Welsh Approved Document B. Any further proposals will be the subject of a public consultation | Not adopted |
| Scotland | At least two escape stairs in every domestic building with a storey more than 18 metres above ground | 1st October 2019 |
The Welsh Government's consultation (opens in a new tab), issued on 17th October 2023, noted that its Approved Document B does not set a threshold above which more than one staircase must be considered for blocks of flats. It asked for evidence on the need for a second staircase above a certain height. The current Welsh Volume 2, at paragraph 3.32, accepts a single common stair in some cases and otherwise expects access to more than one.
The Welsh Government's summary of responses (opens in a new tab), published on 8th January 2025, says most respondents favoured a maximum height for a single stair. Their suggested thresholds varied between 11 and 30 metres. It says the government intends to undertake further research and that any further proposals will be the subject of a public consultation.
In Scotland, the domestic Technical Handbook (opens in a new tab) says at least two escape stairs should be provided to every domestic building with a storey height more than 18 metres above ground level. Its stated purpose is to improve redundancy and escape route options in tall buildings. The 2019 handbook, applying from 1st October 2019, removed the option of a single escape stair for high rise domestic buildings.
Scottish fire guidance sets its own methods of measurement. Clause 2.0.4 gives the example that the topmost storey height for fire and rescue service facilities is measured from the fire and rescue service access level and not necessarily the lowest ground level. Check the Scottish rule for each clause rather than applying Diagram D6. Our fire strategy reports set out the stair, lift and smoke control provisions for residential buildings in each nation. They also test whether a scheme sits inside the English transitional window.
Sources
This guide was written from these official sources. Check the current version before relying on any figure.
- Approved Document B: fire safety, GOV.UK (official source, opens in a new tab)
- Approved Document B 2026 amendments booklet (official source, opens in a new tab)
- Approved Document B Volume 1: Dwellings (official source, opens in a new tab)
- Consultation response: amendments to Approved Document B, second staircases (official source, opens in a new tab)
- Calls for second staircases in all new tall residential buildings, press release (official source, opens in a new tab)
- Approved Document B 2024 amendments: circular 01/2024 (official source, opens in a new tab)
- Approved Document B 2024 amendments: circular letter (official source, opens in a new tab)
- Review of Approved Document B: fire safety guidance, consultation (official source, opens in a new tab)
- Grenfell Tower Inquiry government progress report, September 2026: the construction industry (official source, opens in a new tab)
- Amendments to Part B (fire safety) of the Building Regulations, Welsh Government consultation (official source, opens in a new tab)
- Part B (fire safety) of the Building Regulations: summary of responses, Welsh Government (official source, opens in a new tab)
- Building Standards Technical Handbook, domestic, April 2026 (official source, opens in a new tab)
- Building Standards Technical Handbook 2019, domestic: fire introduction (official source, opens in a new tab)