Invalid, rejected and approved are different outcomes
BSR's figures and guidance use three outcomes that are easy to confuse. Under regulation 5 (opens in a new tab) of the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 an application is valid if it complies with regulation 4, which lists the documents required. If it is not valid, BSR must tell the applicant and give reasons. BSR's data records these applications as invalid, which it defines as applications that do not pass the validation check that all required documents are included.
A rejected application has passed validation and been assessed. BSR has not granted permission to start work. An approved application includes those approved with requirements. BSR's guidance stresses that a validated application has not been approved. Some BSR statements and guidance use the word reject for an application that fails validation. In BSR's published data an application that fails the validation check is counted as invalid, not rejected.
The distinction matters for planning a programme. An invalid application means the validation check found required documents missing. A rejection means BSR has assessed the case and found it does not show compliance, which can mean more detail or redesign. Our Gateway 2 and Gateway 3 support service is set up to prevent both.
The legal grounds for rejection
Regulation 7 (opens in a new tab) says BSR must grant approval unless the application or a document with it falls within one of four grounds. These are the legal grounds for refusal.
- It does not comply with the requirements of regulation 4 or a direction under regulation 59.
- It is not detailed enough for BSR to decide whether the work would contravene the building regulations.
- It shows the work would contravene an applicable requirement of the building regulations.
- It shows the strategies, policies or procedures for change control, mandatory occurrence reporting, competence or sharing information would contravene or be likely to contravene the relevant requirements.
Where a ground applies, BSR may reject the application or, with the applicant's written consent, approve it subject to requirements. A rejection notice must give the reasons. In BSR's guidance (opens in a new tab) the plain version is that applications will be rejected if they do not have enough detail to show compliance or do not show effective strategies for managing compliance. Building work must not start after a rejection. An applicant who disagrees can ask for a review and then appeal to the First-tier Tribunal.
BSR's criteria page (opens in a new tab) lists what it weighs before rejecting. The list includes the complexity of the application, the amount of redesign any clear non-compliance would need, information gaps and how long they would take to fill, how well the application is signposted, the impact on life safety and how requests for information have been answered.
The reasons BSR has published
BSR's building control FAQ (opens in a new tab) lists the issues it commonly finds in rejected applications. Most are about missing or unsupported information rather than unsafe design.
- Proposed layout drawings that conflict with the structural drawings.
- Basic floor plans submitted without any technical detail.
- Supporting documents incomplete or missing, such as major renovation applications with no internal layout or technical drawings.
- Compliance documents missing or simply stating compliance without evidence of how it is achieved.
- Fire safety compliance information not included.
- Construction control plans containing only CDM files instead of the building regulations management information required.
- No policies and procedures for collecting the evidence needed for the completion certificate application.
- A client authorisation without a signed statement that the client agrees to the application and that its information is correct.
BSR's page on getting applications right (opens in a new tab) adds failures to show how the project would meet the golden thread requirements, problems with or absence of a change control plan, dutyholder and competence issues and mandatory occurrence reporting. The guide to who writes a fire strategy covers the competence side.
Three procedural errors are named in BSR's guidance. Uploading a construction phase health and safety plan instead of a construction control plan can lead to rejection. Applying under the wrong work category is likely to lead to rejection. A single application for several higher-risk buildings that are not structurally attached is grounds for rejection.
Fire and structural failures BSR has reported
In a page first published on 28th April 2025, BSR described (opens in a new tab) the technical failings behind rejections. It listed missing details on how key structural components connect, inadequate information on the fire resistance of cladding, walls or barriers, corridors that do not meet evacuation width requirements, poorly designed or unproven smoke extraction and gaps in sprinkler layouts and water supply capacity.
The Part B examples it gave are specific. One smoke extraction design risked pulling smoke from a fire in a flat into the evacuation stairs. The applicant's own smoke analysis showed smoke entering the lobby intended as a safe area. Others had no details of the fire barriers needed in the cladding, corridors too narrow for total evacuation if the fire service recommended it and flats with no smoke detectors, only a heat detector in the kitchen. BSR said it was not rejecting applications over small issues but over serious life safety matters.
The common thread is a fire strategy that asserts an outcome the rest of the package does not support. The guide to the Gateway 2 fire strategy sets out what the fire and emergency file must contain. Where smoke control or evacuation depends on analysis, our smoke control and evacuation modelling service produces evidence a reviewer can test.
What BSR's analysis of rejected applications found
BSR has published an analysis of what it calls a selection of rejected applications, all of them rejected after validation. It puts the figure 42 percent beside that description without saying what it is a share of. It says 45 percent of the new build applications and 50 percent of the existing building applications in that selection were rejected because they did not comply with the building regulations. The page was first published on 24th July 2025 and does not state the period covered or the number of applications.
| Finding | New build applications | Existing building applications |
|---|---|---|
| Did not meet the legal requirements for approval | 73 percent | 80 percent |
| Did not contain sufficient detail | 73 percent | 89 percent |
| Set out work that would contravene the building regulations, including longstanding functional requirements | 45 percent | 50 percent |
| Did not adequately set out how changes would be managed during construction | 27 percent | Not given |
| Set out only a small proportion of the work actually planned | Not given | 43 percent |
The figures overlap because one application can fail on several counts. The pattern is still clear. Lack of detail and failure to meet the legal requirements for approval were the most common findings for both kinds of project, ahead of outright breaches of the regulations.
What the published statistics show over time
BSR publishes application data in a GOV.UK collection (opens in a new tab). Each set covers a stated period and counts invalid, rejected, withdrawn and approved applications separately. The figures below are given as published, for the period and type of work each one covers.
| Period | What it counts | Published figures |
|---|---|---|
| January to March 2025 | All application types decided in the quarter, with invalid and withdrawn counted as decisions | 257 decisions: 82 approved, 62 rejected, 76 invalid and 37 withdrawn |
| January to March 2025 | New build applications decided in the quarter | 23 decisions: 4 approved, 10 rejected, 6 invalid and 3 withdrawn. Median of 36 weeks to approval |
| 12 weeks to 23rd January 2026 | Decisions by BSR's Innovation Unit on new build | 39 decisions with 56 percent invalid. Of those past validation and not withdrawn, 41 percent rejected and 30 percent approved, with the other 23 percent still being managed by account managers |
| 12 weeks to 1st November 2026 | Decisions across all higher-risk building categories, not counting invalid or withdrawn applications | 403 decisions with 370 approved, an approval rate of 92 percent |
| 12 weeks to 1st November 2026 | New higher-risk buildings and conversions | 42 decisions: 40 approved and 2 rejected, 95 percent approval excluding invalidations and withdrawals. 3 invalidated and 1 withdrawn. Median of 20 weeks to approval |
The quarterly workbook (opens in a new tab) published on 9th July 2025 shows that in January to March 2025 invalid and rejected applications together outnumbered approvals. In that quarter only 32.6 percent of decisions subject to a statutory time limit were made within it. The workbook counts invalid and withdrawn applications among its decisions. The 2026 approval rates leave them out. The two sets of figures are therefore not directly comparable.
Two figures from 2025 are still widely quoted. In its page first published on 28th April 2025 BSR said it was having to reject around 70 percent of applications because they did not meet the legal requirements. The same page said its most recent data showed 40 percent of applications being rejected at the validation stage, often because they were missing basic information. BSR gave no period or sample size for either figure and did not say whether the 70 percent included applications that failed validation. In the terms of BSR's own data, the 40 percent describes invalid applications rather than rejections. Both are historical statements from 2025, not current rates.
BSR explained the 2024 backlog as a surge in submissions when transitional arrangements ended, combined with in-flight projects transferred to it when a private building control provider collapsed. The position reported in late 2026 is different. For the rolling 12 weeks to 1st November 2026 BSR reported a 92 percent approval rate across all decisions and 95 percent for new higher-risk buildings and conversions, with a median of 20 weeks to approval for new build. Both rates exclude invalid and withdrawn applications, which BSR counts separately.
What changed at BSR in 2026
BSR moved out of the Health and Safety Executive and became a standalone body sponsored by the Ministry of Housing, Communities and Local Government on 27th January 2026. Its strategic plan for 2026 to 2027 (opens in a new tab), published on 31st March 2026, lists a new account manager role between applicants and the assessment teams, an Innovation Unit to review applications, a pilot of sending batches of applications to the teams and staged Gateway 2 applications for all buildings.
The same plan sets targets for the end of March 2027. For new buildings in non-complex cases BSR expects to respond to a Gateway 2 application in 18 weeks or less with an approval rating of 65 percent. For remediation it expects 12 weeks or less in non-complex cases, also with a 65 percent approval rating.
BSR's remediation plan of 8th April 2026 (opens in a new tab) aims to bring average decision times for remediation applications below 12 weeks by December 2026 with approval rates over 65 percent. It named the gaps behind failed remediation applications. These include insufficient evidence of the fire performance of replacement cladding and membranes, design details promised for later, unsupported non-worsening claims, poorly organised documents and ambiguity over the extent of retained combustible materials.
Building safety levy provisions came into force on 1st October 2026 and BSR reported a surge of applications before that date. BSR's data shows new build applications rising to 64 in September, against 34 in August and 17 in July, then falling to 6 in October. Of the late surge applications that went through enhanced validation, 18 were judged poor quality and paused so the applicant could improve them. A further 8 were recommended for rejection, subject to a final review with the applicant.
How to avoid an invalid or rejected application
BSR's own advice is to Identify, Clarify and Justify. Identify every element within the scope of the regulations. Vague statements such as compliant with Part A are no longer acceptable. Clarify the standards in use and why they were chosen, since simply listing a standard is not enough. Justify the compliance case as an argument, not a list of referenced documents.
- Check every document regulation 4 requires is present, signed and the right document before submission.
- Confirm the work category for an existing building. The wrong category is likely to lead to rejection.
- Submit one application for each structurally attached building and include any shared remote plant room in each.
- Make the architectural, structural and fire drawings agree, since conflicting layouts are a listed reason for rejection.
- Signpost the evidence with a reference file so the key information is not buried in technical reports.
- Give the package to a colleague who has not worked on it and check they can follow the compliance case without sifting through drawings.
- Settle fire service access and water supply before submission. Unresolved fire service concerns should not be deferred through approval with requirements.
- Plan for requests for information. BSR generally expects a response within 48 hours, even if only a holding response. It expects missing information within 2 working weeks.
BSR treats a request for information not answered within 1 working week as a nil response. If a response does not provide what was asked for, BSR will ask once more and then decide the application on its merits, which it says is likely to mean rejection. Approval with requirements is only considered where the design shows substantive compliance and the missing information is minor, clearly defined and does not compromise life safety.
BSR's data page says well-prepared applications progress around 50 percent faster than poorer ones. For existing buildings its guidance says to avoid assumptions and, where one is unavoidable, to support it with survey evidence and a plan to test it on site. Our fire strategy review service checks a strategy against these points before it goes in. Our Gateway 2 and Gateway 3 support service prepares and submits the whole application and handles BSR's requests for information.
Sources
This guide was written from these official sources. Check the current version before relying on any figure.
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 7 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 5 (official source, opens in a new tab)
- Building Control Approval for Higher-Risk Buildings (BSR guidance) (official source, opens in a new tab)
- Getting Building Control Applications Right (BSR) (official source, opens in a new tab)
- Criteria for Validating, Approving or Rejecting Building Control Applications (BSR) (official source, opens in a new tab)
- Building Control FAQ Explainer (BSR) (official source, opens in a new tab)
- BSR in Action: Regulating Higher-Risk Buildings in England (official source, opens in a new tab)
- Building Safety Regulator: Building Control Approval Application Data (collection) (official source, opens in a new tab)
- BSR Building Control Approval Application Data, August to October 2026 (official source, opens in a new tab)
- BSR Building Control Approval Application Data, November 2025 to January 2026 (official source, opens in a new tab)
- BSR Building Control Approval Applications in England, October 2023 to March 2025 (official source, opens in a new tab)
- Building Safety Regulator Strategic Plan 2026 to 2027 (official source, opens in a new tab)
- BSR Plans to Reduce External Remediation Delays (8th April 2026) (official source, opens in a new tab)
- BSR Becomes Standalone Body (27th January 2026) (official source, opens in a new tab)