What counts as a higher-risk building in Wales?
The definition is in the Building Safety (Description of Higher-Risk Building) (Design and Construction Phase) (Wales) Regulations 2023 (opens in a new tab), made on 15th November 2023 and in force from 1st January 2024. Regulation 3 describes a building that is at least 18 metres in height or has at least 7 storeys. It must contain at least one residential unit, a hospital with at least one bed for an overnight stay, a care home or a children's home. It must also not be an excluded building.
Height is measured from ground level to the top of the floor surface of the top storey, ignoring storeys of roof-top plant. A residential unit includes a room in a hostel, a room in a hall of residence or other accommodation for students. Buildings made up entirely of a secure residential institution, a hotel, military barracks or Ministry of Defence or armed forces living accommodation are excluded.
The Welsh test is wider than England's. England's design and construction definition needs at least two residential units, a care home or a hospital. It has no children's home limb. Take a hypothetical 19 metre building with a shop below and a single flat above. In Wales it is a higher-risk building unless it is excluded. Under England's test it is not a higher-risk building because it has only one residential unit.
| Point | Wales | England |
|---|---|---|
| Residential test | At least one residential unit | At least two residential units |
| Other uses caught | A hospital with overnight beds, a care home or a children's home | A care home or a hospital |
| Building control authority | The local authority | The Building Safety Regulator |
Our guide to what a higher-risk building is explains the English test in detail, including how storeys are counted there.
Who approves higher-risk building work in Wales?
In Wales the council approves the work. Under section 121A of the Building Act 1984 (opens in a new tab) the building control authority is the regulator only where section 91ZA or 91ZB says so. In any other case it is a local authority. Section 91ZA (opens in a new tab) makes the regulator the building control authority for higher-risk buildings in England. The Welsh Government (opens in a new tab) states that local authorities are the building control authority for overseeing and approving building work for higher-risk buildings in Wales.
Private approvers are shut out of this work. The Welsh Government's quick guide says registered building control approvers cannot provide building control services for any higher-risk building work. SI 2026/60 made checking plans in relation to higher-risk building work a restricted activity from 1st July 2026. Where a project contains both kinds of building, the local authority is the building control authority for the higher-risk buildings. Either the local authority or a registered building control approver can be the building control body for the rest.
The Building Safety Regulator has a narrower role in Wales than in England. The Welsh Government says it is the main regulator of the building control profession in Wales, acting on behalf of the Welsh Ministers. It adds that the regulator does not oversee building work in Wales. In England an application of this kind goes to the regulator at the stage England calls Gateway 2. In Wales it goes to the council.
The council uses the application to check that the work will comply with building regulations, that the client will manage the project properly and that the people appointed have the competence to do their jobs. Our fire strategy reports for Welsh higher-risk buildings are written with that review in mind.
When approval is needed and who applies
Building control approval is needed before construction of a new higher-risk building starts. It is also needed for work that makes a building a higher-risk building or stops it being one. Work to an existing higher-risk building needs approval unless it consists only of exempt work, competent person scheme work or emergency repairs. The Welsh Government says that carrying out building work without the required approval is a criminal offence.
The client must make sure approval is granted before work starts and that the information in the application is correct. The client may nominate someone to apply. The Welsh Government says the legal responsibility for the application remains with the client.
Projects already in the system can stay on the old rules. The Welsh Government's transitional guidance (opens in a new tab) covers cases where full plans were deposited before 1st July 2026. It also covers an initial notice given and accepted or deemed accepted before that date. In those cases the pre-July rules continue and new provisions such as those on approval stages, the golden thread and dutyholder roles do not apply. That protection ends if the full plans are rejected. It also ends where work has not started within 3 years and the building control authority cancels the initial notice or issues a notice that the deposit of plans has no effect.
For approvals under the new rules, the Welsh Government says approval is lost if the work has not reached a certain point within 3 years of the application date.
What goes in the application
Regulation 4 (opens in a new tab) of the Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025 (opens in a new tab) sets out the application for a new higher-risk building. The regulations were made on 12th December 2025, apply in relation to Wales and came into force on 1st July 2026. The application must be accompanied by the documents below.
- A plan to a scale of not less than 1:1250
- Any other plans needed to show the work would comply with all applicable requirements of the building regulations
- A competence declaration
- A construction control plan
- A change control plan
- A mandatory occurrence reporting plan
- A Building Regulations compliance statement
- A fire and emergency file
- A partial completion strategy, where part of the building is to be occupied before the work is complete
- A statement signed by the client, where someone applies on the client's behalf
The application must also give the height, the number of storeys, the numbers of flats, residential rooms and commercial units, drainage details and a statement of when the work is to be regarded as commenced. A staged application needs a staged work statement describing each stage and estimating when it will start. The Welsh Government advises contacting the building control authority before submitting a staged application.
The fire and emergency file carries the fire strategy. Schedule 1 (opens in a new tab) to the regulations requires it to include the proposed fire strategy demonstrating compliance with paragraphs A3 and B1 to B5 of Schedule 1 to the Building Regulations 2010. It must also include a plan of the fire and rescue service's requirements for access to the building and water supply for firefighting.
The Welsh Government's guidance on preparing the application (opens in a new tab) says the file is often known as a fire strategy. The guidance says it must include plans showing adequate means of escape and warning, measures to inhibit fire spread inside and outside the building and reasonable access and facilities for the fire service. It must set out how building safety risks could affect the building and how the design ensures compliance on structural failure and fire spread. It must also set out how the owner will manage and maintain the building so it can be evacuated, including the occupiers' behaviours.
Work to an existing higher-risk building is either category A or category B. Category A includes changing the height, width or storeys, changing the internal layout or the number of flats or residential rooms, work on external walls, passive or active fire safety measures, work affecting the number or width of staircases or other escape routes and work on common areas. Everything else is category B. Category B work that might affect fire spread needs a fire compliance statement, which the Welsh Government says may also be known as a fire strategy for the work. Applying under the wrong category is likely to lead to rejection.
Fire service consultation and decision times
Before deciding an application the council must consult the enforcing authority for the proposed building under regulation 6 (opens in a new tab). Where requirement H4 applies it must also consult the sewerage undertaker. The plans sent to the enforcing authority must include the fire and emergency file. The council must not decide the application before the end of 15 working days from the start of consultation or any longer period agreed in writing. The bar lifts on the day after the last view is received.
That 15 working day period is unchanged. W.S.I. 2026/112 removed the word working from regulation 15B of the Building Regulations 2010, which governs consultation on other buildings in Wales. It did not change regulation 6 of SI 2025/1321. Our guide to fire strategy in Wales covers regulation 15B.
The decision periods are set out below. The Welsh Government circular WGC 002/2026, issued on 6th January 2026, gives the same figures of 12 weeks for a new higher-risk building and 8 weeks for work to an existing one.
| Step | Regulation | Time limit |
|---|---|---|
| Application for a new higher-risk building | Regulation 5 | 12 weeks from receipt or a longer period agreed in writing |
| Application for work to an existing higher-risk building | Regulation 13 | 8 weeks from receipt or a longer period agreed in writing |
| Fire service consultation before approval | Regulation 6 | No decision before the end of 15 working days unless all views are in |
| Completion certificate application | Regulation 40 | 8 weeks from receipt or a longer period agreed in writing |
| Fire service consultation before completion | Regulation 41 | No decision before the end of 15 working days unless all views are in |
Under regulation 7 (opens in a new tab) approval must be granted unless the application fails regulation 4, is not sufficiently detailed or shows the work would contravene the building regulations. It can also be refused where the strategies for controlled changes, the golden thread, mandatory occurrence reporting or dutyholders and competence would be likely to contravene the rules. With the applicant's written consent the council may instead grant approval subject to requirements.
The Welsh Government says assessment time depends on the quality of the application and the complexity of the work. A fire and emergency file that reads clearly against the Welsh guidance is the part most within the applicant's control.
During construction: notices, change control and reporting
Once approval is granted, notices mark the progress of the work. A notice of intention to start work is due at least 5 working days before starting. A notice of commencement is due within 5 working days after the day the work is regarded as commenced. Further notifications follow as the work reaches the points set in the inspection schedule.
Approved documents become agreed documents and any change to them is a controlled change recorded in the change control log. The Welsh Government says that for a major change, work must stop on that part of the project until the building control authority approves the change. A fire strategy that leaves key decisions open at application stage tends to produce controlled changes later.
The mandatory occurrence reporting plan must describe the reporting systems run by the principal designer and principal contractor. It covers incidents or risks that have caused or are likely to cause the death or serious injury of a significant number of people through structural failure or the spread of fire or smoke.
Emergency repairs are not a route around approval. The Welsh Government says they should not be used to fix problems caused by a lack of foresight or planning. It adds that work to comply with a fire service enforcement notice is unlikely to count. After an emergency repair a regularisation certificate must be applied for as soon as possible.
Completion and handover
At the end of the work the council decides a completion certificate application within 8 weeks of receipt under regulation 40 (opens in a new tab) or within a longer agreed period. Before deciding, it must consult the enforcing authority under regulation 41 (opens in a new tab). In England this is the stage known as Gateway 3, decided by the regulator.
Under regulation 37 (opens in a new tab) the client must give the responsible person the fire safety information and specified golden thread information no later than the date the work is completed. The responsible person acknowledges receipt. W.S.I. 2026/112 substituted the definition of fire safety information in SI 2025/1321 from 20th July 2026. It now covers the design and construction of the building and its services, fittings and equipment, the design of any material change of use and the composition of materials used, where that will help the responsible person operate and maintain the building with reasonable safety.
Charges for applications are published by each local authority. W.S.I. 2026/112 also amended the local authority charges regulations so that councils can charge for certain applications under SI 2025/1321. If you disagree with a decision you can request a review and then appeal to the Welsh Ministers.
The Building Safety (Wales) Act 2026 and occupied buildings
Occupied buildings in Wales will be covered by a separate Welsh Act. The Building Safety (Wales) Act 2026 (opens in a new tab) was passed by the Senedd on 10th March 2026 and received Royal Assent on 27th April 2026. It makes provision for the safety of people in or about buildings containing two or more residential units and certain houses in multiple occupation. The Building Safety Regulator has no role under it.
The Welsh Government says the Act requires regulated buildings at least 11 metres high or with at least 5 storeys to be registered with a building safety authority. The Welsh Ministers will designate one council in each fire and rescue authority area as the building safety authority. Each Welsh fire and rescue authority will be the fire safety authority, with a fire inspector taking that role for Crown premises. The Act creates duties to assess and manage fire safety risks in regulated buildings and relevant houses in multiple occupation. It also creates structural safety duties for buildings of at least 11 metres or 5 storeys.
- Category 1: at least 18 metres or at least 7 storeys
- Category 2: under 18 metres and under 7 storeys, with at least 11 metres or at least 5 storeys
- Category 3: under 11 metres and under 5 storeys
Section 6, which sets those categories, came into force on 28th April 2026 with a small group of other sections. Under section 138 (opens in a new tab) the other provisions come into force on a day the Welsh Ministers appoint by order. No commencement order under the Act appears among the 2026 Welsh statutory instruments on legislation.gov.uk at 23rd November 2026. Its occupation duties, including registration and safety case reports, are therefore not yet in force as at 23rd November 2026.
Once commenced, section 37 will require the principal accountable person for an occupied category 1 building to prepare a safety case report and give a copy to the building safety authority. Our guide to what a building safety case is compares that with the regime in England. Section 139 requires the Welsh Ministers to report on progress in bringing the Act into force until it is fully in force.
Why applications are rejected and what to check first
The Welsh Government says an application will be rejected if it shows the work will not comply with building regulations. It also says applications will be rejected if they do not have enough detail to show compliance or do not show effective strategies for managing compliance.
- Confirm whether the building meets the Welsh test, which needs only one residential unit and includes children's homes.
- Apply to the local authority rather than the Building Safety Regulator. Do not appoint a registered building control approver for the higher-risk work.
- Check whether the project was submitted before 1st July 2026 and still benefits from the transitional rules.
- Choose category A or category B correctly for work to an existing higher-risk building.
- Write the fire and emergency file to the Welsh Approved Document B and the Welsh regulations, not England's.
- Build the 15 working day fire service consultation and the 12 week or 8 week decision period into the programme.
Our Wales page covers projects across the country.
If you are preparing an application, our fire strategy report service writes the fire and emergency file to the Welsh rules. Where a design departs from the guidance, our fire engineering service sets out the case.
Where a strategy was written for an English application or before 1st July 2026, a fire strategy review checks it against the Welsh procedures before it goes to the council.
Sources
This guide was written from these official sources. Check the current version before relying on any figure.
- Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025, regulation 4 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025, regulation 5 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025, regulation 6 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025, regulation 13 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025, regulation 40 (official source, opens in a new tab)
- Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025, regulation 41 (official source, opens in a new tab)
- Building Safety (Description of Higher-Risk Building) (Design and Construction Phase) (Wales) Regulations 2023, regulation 3 (official source, opens in a new tab)
- Building Act 1984, section 121A (official source, opens in a new tab)
- Building control approval for higher-risk buildings (Welsh Government) (official source, opens in a new tab)
- Preparing information for a building control approval application for a higher-risk building (Welsh Government) (official source, opens in a new tab)
- Transitional arrangements for the new building control regime starting 1st July 2026 (Welsh Government) (official source, opens in a new tab)
- Building Safety (Wales) Act 2026 (Welsh Government) (official source, opens in a new tab)
- Building Safety (Wales) Act 2026, section 138 (official source, opens in a new tab)